Guadalupe Area Projects

Facebook IconTwitter(X) IconInstagram IconYoutube Icon

Public Meeting In Person

January 21, 2026 5:30-7:00 PM
Guadalupe City Hall
918 Obispo Street
Guadalupe, CA 93434

Spanish translation will be available. Doors open at 5:15 PM

Map showing the various Guadalupe Area Caltrans projects along state route 1 and 166

Project Description

This project is on State Route 1 at Oceano from the Santa Maria Bridge to Garcia Way. The project aims to preserve more than 20 miles of pavement using Capital Preventative Maintenance Strategies. The project would upgrade drainage systems and guardrail and incorporate complete streets and ADA features.

Proposed Project Schedule

Process Date
Final environmental document to be completed November 2029
Right-of-way acquisition to be completed February 2031
Design to be completed May 2031
Advertise January 2032
Construction to begin Spring 2032
Construction to be completed Summer 2032

Estimated Funding Breakdown

Funding Source Funding Amount
Construction Capital Cost $33,880,000

Project Contact

Ben Jensen, Project Manager
Phone: (805) 788-8978
Email: ben.jensen@dot.ca.gov

Project Description

This project would preserve four plus miles of pavement using Capital Preventative Maintenance strategies. This project would also replace sign panels.

Proposed Project Schedule

Process Date
Final environmental document to be completed March 2026
Right-of-way acquisition to be completed June 2028
Design to be completed July 2028
Advertise November 2028
Construction to begin Spring 2029
Construction to be completed Fall 2029

Estimated Funding Breakdown

Funding Source Funding Amount
Construction Capital Cost $2,311,000 (preliminary estimate)

Project Contact

Hallie Holden, Project Manager
Phone: (916) 995-1421
Email: hallie.holden@dot.ca.gov

Project Description

This project would preserve 20 plus miles of pavement using Capital Preventative Maintenance strategies. This project would add shoulder backing, curb ramps, drainage systems and count stations. In addition, it would signalize state route 1/166 and state route 166/Obispo Street intersection. The project would also install complete streets elements along state route 166 from state route 1 to Flower Avenue.

Proposed Project Schedule

Process Date
Final environmental document completed August 2024
Right-of-way acquisition to be completed July 2027
Design to be completed July 2027
Advertise December 2027
Construction to begin Spring 2028
Construction to be completed Fall 2029

Estimated Funding Breakdown

Funding Source Funding Amount
Construction Capital Cost $35,000,000

Project Contact

Hallie Holden, Project Manager
Phone: (916) 995-1421
Email: hallie.holden@dot.ca.gov

Project Description

This project would add ADA pedestrian infrastructure improvements including upgrade driveways, curb ramps, and sidewalks.

Proposed Project Schedule

Process Date
Final environmental document completed April 2022
Right-of-way acquisition completed June 2025
Design completed June 2025
Advertised November 2025
Construction to begin Winter 2025
Construction to be completed Spring 2028

Estimated Funding Breakdown

Funding Source Funding Amount
Construction Capital Cost $10,800,000

Project Contact

Hallie Holden, Project Manager
Phone: (916) 995-1421
Email: hallie.holden@dot.ca.gov

Project Description

This project would replace the existing bridge and would utilize an aesthetic surface treatment of the structure.

Proposed Project Schedule

Process Date
Final environmental document completed December 2020
Right-of-way acquisition completed December 2024
Design completed June 2024
Advertise April 2025
Construction began Fall 2025
Construction to be completed Summer 2032

Estimated Funding Breakdown

Funding Source Funding Amount
Construction Capital Cost $6,133,400

Project Contact

Ben Jensen, Project Manager
Phone: (805) 788-8978
Email: ben.jensen@dot.ca.gov

Project Description

This project is at the intersection of State Route 1 and State Route 166, south on State Route 1 to Solomon Road. The project aims to widen shoulders, add rumble strips, update the guardrail, and relocate utility poles.

Proposed Project Schedule

Process Date
Final environmental document completed July 2021
Right-of-way acquisition completed June 2025
Design completed April 2023
Advertised November 2025
Construction to begin Spring 2026
Construction to be completed Fall 2027

Estimated Funding Breakdown

Funding Source Funding Amount
Construction Capital Cost $21,607,000

Project Contact

Ben Jensen, Project Manager
Phone: (805) 788-8978
Email: ben.jensen@dot.ca.gov

Documents

Accessibility Assistance: Caltrans makes every attempt to ensure our documents are accessible. Due to variances between assistive technologies, there may be portions of this document which are not accessible. Where documents cannot be made accessible, we are committed to providing alternative access to the content. Should you need additional assistance, please contact us at (916) 654-2852 or visit https://dot.ca.gov/request-ada-compliant-documents.

Title VI Information

The California Department of Transportation (Caltrans) assures that no person shall, on the basis of race, color, or national origin, be excluded from participation in, be denied the benefits of, or be otherwise subjected to discrimination under any program or activity receiving Federal financial assistance, as required by Title VI of the Civil Rights Act of 1964, as amended, the Civil Rights Restoration Act of 1987, and Federal Executive Order 12898 (Federal Actions to Address Environmental Justice in Minority Populations and Low-Income Populations).

Caltrans will make every effort to ensure nondiscrimination in all of its programs and activities, whether they are federally funded or not, and that services and benefits are fairly distributed to all people, regardless of race, color, or national origin. In addition, Caltrans will facilitate meaningful participation in the transportation planning process in a nondiscriminatory manner.

Title VI Brochures

Title VI brochures in various languages