Overnight Paving Operation and Daytime Work Continues on State Route 183/Merritt Street in Castroville

Published:

California highway 183 shield.

Date: Friday, November 13, 2026
District: 05 - Santa Barbara, San Luis Obispo, Monterey, San Benito, and Santa Cruz Counties
Contact: Heidi Crawford or Mariana Holder or Ashton Harris
Phone: (805) 549-3318

Overnight Paving Operation and Daytime Work Continues on State Route 183/Merritt Street in Castroville

MONTEREY COUNTY – Construction continues and is working towards completion on a major rehabilitation of State Route 183 (Merritt Street) in Castroville to enhance multimodal travel. This primary phase of work will result in nighttime resurfacing and paving of SR 183 beginning at the south end of Del Monte Avenue and working northward to State Route 1. After PG&E completed their work within the sidewalk areas, Granite then completed the sidewalk construction.

Reminder: Drivers must abide by speed limit laws everywhere.

At least one lane of traffic in each direction will remain open for travelers on SR 183 during night work closures. Paving on Merritt Street has been completed. Some paving on side streets where they connect with Merritt Street is still needing to be done. Contractors will work to place final and permanent striping configurations, install traffic signal control loops within the roadway, and work to raise ground utilities boxes to the new roadway grades. The landscape subcontractor will continue to install irrigation system and prepare the tree wells to start planting trees and other plants. The pedestrian railings will be installed in place once the fabrication is completed. Placement of concrete for curb and gutters, and ADA ramps was completed in most of the locations.

Overnight road work with alternating lane closures will continue from Del Monte Avenue to State Route 1 from 8 pm to 5 am. This work consists of grinding, resurfacing and paving. After completing paving, the electrical work will begin to install traffic signals control loops. Striping work will take place to then apply the final stripe configuration.

All businesses remain open and Caltrans appreciates the patience of the business community and the people of Castroville.

A zone for construction workers and two-way traffic will be maintained with minor delays and will include heavy equipment. During some stages of construction, there will be a temporary removal of parking, sidewalk and driveway access. Pedestrian access to local businesses and residences will be provided and maintained by the Contractor. Bicyclists and motorists are encouraged to share the road on SR 183. Travelers can expect delays of up to 15 minutes during peak periods. Plan your travel accordingly. 

Message and directional signs will direct travelers in advance of the project area.

About the Project

Through the town of Castroville on Merritt Street, the project will rehabilitate the pavement, address essential bridge maintenance needs, and improve multimodal features, including transit stops, sidewalks, driveways, and ADA compliant curb ramps. The project will also install new Intelligent Transportation System features and improve aesthetics, bicycle network continuity, and pedestrian safety.

Updates for the SR183/Merritt Street Castroville Improvement Project can be found at:

State Route 183 Castroville Improvement Project | Caltrans

The contractor for this $38 million project is Granite Construction, Inc. out of Watsonville, CA. The construction stage of this project is expected to be complete by end of 2026.

Road information and updates can also be found on Caltrans Central Coast District 5 Social Media Platforms: X at @CaltransD5, Facebook at: Caltrans Central Coast (District 5) and Instagram at: Caltrans_D5.

Our crews deserve to get home safely too.
Drive slowly and carefully in work zones.