Most Project Timelines, Budgets Met
Highway Improvement Program Achieves 24 of 25 Delivery Milestones in 2018-19

During the 2018-19 fiscal year, Caltrans chalked up a 96 percent on-time performance rate delivering state highway projects that receive funding from the State Transportation Improvement Program (STIP). All but one of 25 schedule milestones were met for the projects defined as costing more than $1 million apiece and for which Caltrans is responsible for all development work.
Caltrans, though its Project Delivery division, completed construction on 23 STIP projects on the State Highway System in 2018-19, with total costs approximately $34 million (3 percent) over the original allocation. All overruns were authorized through the change control process approved by the California Transportation Commission (CTC).

The STIP funds state highway, local road, non-motorized transportation, transit, and intercity rail improvements. The 2020 STIP makes available nearly $2.6 billion over five years for local and state transportation projects. Caltrans’ Division of Local Assistance works with regional planning agencies on applications for STIP transportation funding in those areas, and issues a separate report on project activities.
Caltrans awarded construction contracts for six STIP projects on the State Highway System in 2018-19 valued at $725 million. To get those projects developed, designed and delivered to construction, Caltrans spent $100 million in staff time and expenses. This means that the support dollars needed to deliver those projects was 13.8 percent compared with the capital dollars required for construction. By statute, Caltrans is limited to a ratio of 20 percent or less when comparing the support dollars to deliver projects with the capital dollars required to build them.
An annual status report on the schedule and costs of Caltrans’ capacity-enhancing State Highway System projects must be presented to the governor and Legislature by Nov. 15. The completed 2018-19 report is available online.
During the previous fiscal year, in 2017-18, Caltrans met all eight of its schedule milestones, the actual costs of projects completed were less (by $224 million, or 14 percent) than originally allocated by the CTC, and projects awarded construction achieved the 20-percent support-to-capital ratio goal.

The lone milestone that Caltrans did not meet in 2018-19 was the target date of June 17, 2019, for advertising for construction a project in Tuolumne County on State Route 108. The reason given was the inability to secure a utility agreement for relocation of an electrical vault.
Under STIP guidelines, Caltrans is committed toward meeting six categories of schedule milestones for a project: commencement of the environmental process; commencement of the circulation of the draft environmental documents; final approval of the environmental documents; commencement of work on the plans, specifications and estimates; project ready to advertise for construction; and project advertised for construction.
The average support-to-capital ratio for Caltrans’ STIP projects delivered over the last three fiscal years is 16.9 percent.
Project delivery reports on other programs, such as State Highway Operation and Protection Program known as SHOPP, the Department’s main source of highway repair and rehabilitation funds, are provided to the California Transportation Commission and the Legislature.
Source: Fiscal Year 2018-19 Project Delivery Report for the State Transportation Improvement Program.
- Director's Message
- Mile Markers
- Creating Safer Corridors
- Clean-Air Travel Options Expanding
- Caltrans, Partners Push More Inclusive Safety Plan
- Connecting the (Data) Dots
- Project Spotlight: Washed-Out Roads Isolate Town, Put Caltrans to the Test
- Caltrans Strives for Fairness, Inside and Out
- Highway System Gets Good Marks on Report Card
- Mileposts
- Most Project Timelines, Budgets Met
- Garbage a Growing Distraction for Caltrans
- COVID-19 Update