Contract Time
Example Weekly Statement of Working Days
The following are examples of typical entries for Form CEM-2701, “Weekly Statement of Working Days.”
For more information regarding administration of contract time, refer to Section 3-8, "Prosecution and Progress," (PDF) of the Construction Manual.
-
First Working Day/Begin Work (PDF)
-
Time Adjustment (PDF)
-
Revised Weekly Statement of Working Days for Nonworking Day (PDF)
-
Nonworking Day Due to Temporary Suspension (PDF)
-
Excusable and Critical Delay (PDF)
-
Contract Overrun (PDF)
- Type 1 Plant Establishment - Non-Plant Establishment Work Completed
-
Type 1 Plant Establishment - Plant Establishment Work Completed (PDF)
-
Type 2 Plant Establishment Period Begins – Highway Work Not Completed (PDF)
-
Type 2 Plant Establishment Period Ends – Highway Work Not Completed (PDF)
-
Calendar Day Project (PDF)
Working Day Calendar Through the Year 2035
The Working Day Calendar is used to compute the estimated completion date of a contract. To use the calendar, find the start date of the contract, add the working days to the number of the calendar date (a number from 1 to 1000), and subtract 1, find that calculated number in the calendar and that will be the estimated completion date of the contract.
NOTE!! Holidays are defined in Section 1-1.04B, "Glossary," of the Standard Specifications. As of 1997, the government code added Cesar Chavez Day, March 31. All of the printed and on line work day calendars are incorrect if they do not designate March 31 as a non-work day.
NOTE!! As of March 1, 2008, the day after Thanksgiving is considered a nonworking day.