Overnight Closures Scheduled Dec. 8-13 at State Route 91 from Cerritos to Gardena for Sign Rehabilitation Project

Published:

Los Angeles— Caltrans is planning overnight connector and lane closures along State Route 91 (SR-91) from Cerritos to Gardena in Los Angeles County, starting Monday Dec. 8 through Saturday Dec. 13, for k-rail installation for a sign rehabilitation project.

Westbound SR-91 will be reduced to four lanes overnight between Interstate 605 (I-605) in Cerritos and Vermont Avenue in Gardena. Eastbound SR-91 will be reduced to two lanes overnight from Vermont Avenue in Gardena to Interstate 710 (I-710) and I-605 in Cerritos, to the Orange County line at postmile (PM) 20.7. Eastbound SR-91 will be reduced to three lanes overnight between I-710 and I-605.

There will be overnight full closures of I-605 and Interstate 110 (I-110) connectors to SR-91, and Eastbound SR-91 connectors to I-605 and I-110.

The closures are subject to change and are scheduled as follows:

Monday night, Dec. 8 through Friday morning, Dec. 12

Westbound SR-91

  • Closure of three right lanes on westbound SR-91 from Atlantic Avenue to Vermont Avenue from 9 p.m. to 5 a.m. daily
  • Closure of two right lanes on westbound SR-91 from I-605 to Atlantic Avenue from 9 p.m. to 5 a.m. daily
  • Westbound SR-91 connector to northbound I-110 will be fully closed from 9 p.m. to 5 a.m. daily
  • Westbound SR-91 connector to southbound I-110 will be fully closed from 10 p.m. to 5 a.m. daily
  • Closure of westbound SR-91 on-ramp at Main Street from 9 p.m. to 6 a.m. daily
  • Closure of westbound SR-91 on-ramp at Downey Avenue from 9 p.m. to 5 a.m. daily

Eastbound SR-91

  • Closure of two right lanes on eastbound SR-91 from I-710 to I-605, from 10 p.m. to 5 a.m. daily
  • Closure of two right lanes on eastbound SR-91 from I-605 to the Orange County line at PM 20.7, from 11:59 p.m. to 4 a.m. daily
  • Closure of eastbound SR-91 on-ramp at Cherry Ave from 9 p.m. to 5 a.m. daily
  • Closure of eastbound SR-91 off-ramp at Paramount Boulevard from 11 p.m. to 5 a.m. daily

Southbound I-605

  • Southbound I-605 connector to westbound SR-91 will be fully closed from 8 p.m. to 4 a.m. daily
  • Southbound I-605 connector to eastbound SR-91 will be fully closed from 11 p.m. to 4 a.m. daily

Friday night, Dec. 12 through Saturday morning, Dec. 13

Westbound SR-91

  • Closure of three right lanes on westbound SR-91 from Atlantic Avenue to Vermont Avenue from 9 p.m. to 10 a.m.
  • Closure of two right lanes on westbound SR-91 from I-605 to Atlantic Avenue from 9 p.m. to 9 a.m.
  • Westbound SR-91 connector to northbound I-110 will be fully closed from 10 p.m. to 8 a.m.
  • Westbound SR-91 connector to southbound I-110 will be fully closed from 11 p.m. to 6 a.m.
  • Closure of westbound SR-91 on-ramp at Main Street from 9 p.m. to 9 a.m.
  • Closure of westbound SR-91 on-ramp at Downey Avenue from 9 p.m. to 9 a.m.

Eastbound SR-91

  • Closure of two right lanes on eastbound SR-91 from I-710 to I-606, from 11 p.m. to 7 a.m.
  • Closure of two right lanes on eastbound SR-91 from I-605 to the Orange County line at PM 20.7, from 1:00 a.m. to 5 a.m.
  • Closure of eastbound SR-91 on-ramp at Cherry Ave from 10 p.m. to 5 a.m. daily
  • Closure of eastbound SR-91 off-ramp at Paramount Boulevard from 11:59 p.m. to 5 a.m.

Southbound I-605

  • Southbound I-605 connector to westbound SR-91 will be fully closed from 8 p.m. to 8 a.m
  • Southbound I-605 connector to eastbound SR-91 will be fully closed from 11:59 p.m. to 6 a.m.

Monday night, Dec. 8 through Saturday morning, Dec. 13

Westbound SR-91

  • Closure of westbound SR-91 off-ramp at Main Street from 9 p.m. to 6 a.m. daily
  • Closure of westbound SR-91 off-ramp at Long Beach Boulevard from 9 p.m. to 6 a.m. daily

Eastbound SR-91

  • Closure of two right lanes on eastbound SR-91 from Vermont Avenue to I-710, from 11 p.m. to 5 a.m. daily
  • Eastbound SR-91 connector to southbound I-110 from 9 p.m. to 6 a.m. daily
  • Eastbound SR-91 connector to northbound I-110 from 9 p.m. to 6 a.m. daily
  • Eastbound SR-91 connector to southbound I-605 from 9 p.m. to 6 a.m. daily
  • Eastbound SR-91 connector to northbound I-605 from 10 p.m. to 6 a.m. daily
  • Closure of eastbound SR-91 off-ramp at Main Street from 9 p.m. to 6 a.m. daily
  • Closure of eastbound SR-91 on- and off-ramps at Long Beach Boulevard from 9 p.m. to 6 a.m. daily
  • Closure of eastbound SR-91 on-ramp at Paramount Boulevard from 9 p.m. to 6 a.m. daily

Northbound I-605

  • Northbound I-605 connector to eastbound SR-91 will be fully closed from 9 p.m. to 6 a.m. daily

Message signs will be placed along detour routes to direct traffic. Caltrans encourages motorists to allow extra travel time and to drive with caution in the area.

Due to weather or operational reasons, the schedule is subject to change including the times and dates, the number of closures and other details. Residents and businesses located near construction may experience noise, vibrations and dust associated with construction activities. Please visit Quickmap for current road conditions.

This project will rehabilitate and upgrade roadside and overhead enhance signs and lighting, restore highway planting, replace guardrail, and make worker safety improvements along 14.7 miles of SR-91 in Los Angeles County. The cost of the project is $34 million. Construction is expected to complete in summer 2029. The contractor is Security Paving Company, Inc.

Sign up for notifications about the project. If you have already signed up and are receiving project emails, there is no need to sign up again.

Caltrans reminds drivers to “Be Work Zone Alert” and to “Slow for the Cone Zone.”