Upper Drainage Erosion Control Improvements

Project Description

The California Department of Transportation (Caltrans) is proposing to replace or repair drainage systems along Highway 9 from Ben Lomond to Highway 35 that have been determined to be deficient. The project would replace and/or reconstruct drainage inlets, install new pipe culverts, fill and abandon old culverts, repair outlets, place rock slope protection, rebuild and lengthen a retaining wall, and repair trail erosion. 

Proposed Project Schedule

  • Funding Allocation: August 2024
  • Advertising: September 2024
  • Begin construction: February 2025
  • Complete construction: August 2027

Construction Cost

  • $8,500,0000