San Joaquin River Garwood Bridge Rehabilitation Project
Project Description
The California Department of Transportation proposes to address structural and maintenance deficiencies on and near the existing San Joaquin River (Garwood) Bridge, Bridge Number 29-0050, located within the City of Stockton and south of the Port of Stockton. The work recommendations to address the structural deficiencies include replacing the damaged members of the west portal sway bracing with new members, removing and replacing the left and right curb along the bridge, and patching the spalls in the polyester concrete overlay along Westbound Lane and also along the soffit of the west end abutment area. The maintenance deficiencies consist of removal of underwater debris from bridge center column in the water, providing erosion control along the eastern abutment retaining wall, and enhancing safety lighting along the approach and departure and at the Roberts Road Intersection
Project Benefits
Purpose
The purpose of the project is to improve bridge-related structural and maintenance deficiencies.
Need
The project is needed to address structural and maintenance deficiencies associated with the San Joaquin River Garwood Bridge (Bridge Number 29¬0050). The deficiencies include the following:
Structural Deficiencies:
- Damaged west portal overhead steel bracing members
- Undesirable movement occurring in right bearing at Abutment 1 on west side of bridge
- Spalls in the bridge concrete deck surface near the west end of the bridge in westbound direction
- Bridge operator house on the north side of the bridge is damaged and non-operable
- Debris buildup in the central portion of the San Joaquin River channel adjacent to the center column/foundation
- Lack of lighting at approaches and departures of the bridge and at the adjacent Roberts Lane intersection
- Erosion along the toe of the east side abutment
Documents
Initial Study with Negative Declaration Volume 1 of 2
Notice of Completion & Environmental Document Transmittal
Current Schedule
Summer 2018 (A)
Project Study Report (M010)
Summer 2024
Project Approval & Environmental Document (M200)
Spring 2025
Right of Way Certification (M410)
Summer 2025
Ready to List (M460)
Spring 2026
Approved Construction Contract (M500)
Winter 2026
Project Completion (M600)
Funding Source
SHOPP 201.110 (Bridge Rehab. And Replacement Program)
Project Status
Project is currently in PA&ED phase.
Project Cost/Programmed (x$1,000):
Programed Project Cost | Capital $ | Support $ |
---|---|---|
Project Approval & Environmental Document | $3,359 | |
Plans, Specifications, & Estimates | $1,030 | |
Right of Way | $30 | $4 |
Construction | $7,427 | $1,051 |
Projected Cost as of April 24, 2024: | Planned $ | Expended $ |
---|---|---|
Project Approval & Environmental Document | $3,359 | $1,473 |
Plans, Specifications, & Estimates | $1,030 | $0 |
Right of Way | $34 | $0 |
Construction | $2,300 | $0 |