State Route 4 Garwood Bridge Rehabilitation Project
Public Notice
Project Description
The California Department of Transportation proposes to address the structural deficiencies on the existing San Joaquin River Garwood Bridge (Bridge Number 29-0050). The proposed work includes replacing the damaged members of the west portal sway truss bracing with new members, removing the bridge operator house, patching the spalls in the polyester concrete overlay along the westbound lane and along the soffit of Bay 4 in Span 3, and resetting the bridge abutment bearing to prevent the undesirable movement occurring in the right bearing at Abutment 1.
![State Route 4 Garwood Bridge Rehabilitation Project Map](/-/media/dot-media/district-10/images/projects/10-1h200-state-route-4-garwood-bridge-rehabilitation-project/10-1h200-locmap3.png?h=600&w=600&hash=168FEC260D37BAB252CA8806D27B61D8)
Project Benefits
Purpose and Need
The purpose of the project is to improve bridge-related structural and maintenance deficiencies. The project is needed to address structural and maintenance deficiencies associated with the San Joaquin River Garwood Bridge (Bridge Number 29-0050). The deficiencies include the following:
Structural Deficiencies:
- Damaged west portal overhead steel bracing members
- Undesirable movement occurring in right bearing at Abutment 1 on west side of bridge
- Spalls in the bridge concrete deck surface near the west end of the bridge in westbound direction
Maintenance Deficiencies:
- Bridge operator house on the north side of the bridge is damaged and non-operable
- Debris buildup in the central portion of the San Joaquin River channel adjacent to the center column/foundation
- Lack of lighting at approaches and departures of the bridge and at the adjacent Roberts Lane intersection.
- Erosion along the toe of the east side abutment.
Funding Source
SHOPP 201.110 (Bridge Rehab. And Replacement Program)
Project Cost/Programmed (x$1,000):
Programed Project Cost | Capital $ | Support $ |
---|---|---|
Project Approval & Environmental Document | $0 | $3,359 |
Plans, Specifications, & Estimates | $0 | $1,030 |
Right of Way | $30 | $4 |
Construction | $7,427 | $1,051 |
Projected Cost as of 04/24/2024 | Planned $ | Expended $ |
---|---|---|
Project Approval & Environmental Document | $3,359 | $1,473 |
Plans, Specifications, & Estimates | $1,030 | $0 |
Right of Way | $34 | $0 |
Construction | $2,300 | $0 |
Current Schedule
Process | Date |
---|---|
Project Study Report (M010) | Summer 2018 (A) |
Project Approval & Environmental Document (M200) | Summer 2024 |
Right of Way Certification (M410) | 4/17/2026 |
Ready to List (M460) | 5/22/2026 |
Approved Construction Contract (M500) | 11/30/2026 |
Project Completion (M600) | 3/5/2027 |
*Milestone Achieved (A) |
Project Status
Project is currently in PA&ED phase.
Documents
Initial Study with Proposed Negative Declaration Volume 1 of 2
Notice of Completion & Environmental Document Transmittal
Project Contact
Caltrans District 10 - Program Project Management
Udaya (Sam) Shankar, Project Manager
Phone: (209) 639-6456
Email: udaya.shankar@dot.ca.gov
Caltrans District 10 - Public Information Office
Phone: (209) 948-7977
Email: district10publicaffairs@dot.ca.gov
Address: P.O. Box 2048, Stockton, CA 95201-2048
Title VI Information
The California Department of Transportation (Caltrans) assures that no person shall, on the basis of race, color, or national origin, be excluded from participation in, be denied the benefits of, or be otherwise subjected to discrimination under any program or activity receiving Federal financial assistance, as required by