State Route 4 Garwood Bridge Rehabilitation Project

Public Notice

Project Description

The California Department of Transportation proposes to address the structural deficiencies on the existing San Joaquin River Garwood Bridge (Bridge Number 29-0050). The proposed work includes replacing the damaged members of the west portal sway truss bracing with new members, removing the bridge operator house, patching the spalls in the polyester concrete overlay along the westbound lane and along the soffit of Bay 4 in Span 3, and resetting the bridge abutment bearing to prevent the undesirable movement occurring in the right bearing at Abutment 1.

State Route 4 Garwood Bridge Rehabilitation Project Map 

Project Benefits

Purpose and Need

The purpose of the project is to improve bridge-related structural and maintenance deficiencies. The project is needed to address structural and maintenance deficiencies associated with the San Joaquin River Garwood Bridge (Bridge Number 29-0050). The deficiencies include the following:

Structural Deficiencies:

  • Damaged west portal overhead steel bracing members
  • Undesirable movement occurring in right bearing at Abutment 1 on west side of bridge
  • Spalls in the bridge concrete deck surface near the west end of the bridge in westbound direction

Maintenance Deficiencies:

  • Bridge operator house on the north side of the bridge is damaged and non-operable
  • Debris buildup in the central portion of the San Joaquin River channel adjacent to the center column/foundation
  • Lack of lighting at approaches and departures of the bridge and at the adjacent Roberts Lane intersection.
  • Erosion along the toe of the east side abutment.

 

Funding Source

SHOPP 201.110 (Bridge Rehab. And Replacement Program)

 

Project Cost/Programmed (x$1,000):

Programed Project Cost Capital $ Support $
Project Approval & Environmental Document $0 $3,359
Plans, Specifications, & Estimates $0 $1,030
Right of Way $30 $4
Construction $7,427 $1,051

 

Projected Cost as of 04/24/2024 Planned $ Expended $
Project Approval & Environmental Document $3,359 $1,473
Plans, Specifications, & Estimates $1,030 $0
Right of Way $34 $0
Construction $2,300 $0

 

Current Schedule

Process Date
Project Study Report (M010) Summer 2018 (A)
Project Approval & Environmental Document (M200) Summer 2024
Right of Way Certification (M410) 4/17/2026
Ready to List (M460) 5/22/2026
Approved Construction Contract (M500) 11/30/2026
Project Completion (M600) 3/5/2027
*Milestone Achieved (A)  

 

Project Status

Project is currently in PA&ED phase.

 

Documents

Initial Study with Proposed Negative Declaration Volume 1 of 2

Notice of Completion & Environmental Document Transmittal

 

Project Contact

Caltrans District 10 - Program Project Management
Udaya (Sam) Shankar, Project Manager
Phone: (209) 639-6456
Email: udaya.shankar@dot.ca.gov

Caltrans District 10 - Public Information Office
Phone: (209) 948-7977
Email: district10publicaffairs@dot.ca.gov
Address: P.O. Box 2048, Stockton, CA 95201-2048

 

Title VI Information

The California Department of Transportation (Caltrans) assures that no person shall, on the basis of race, color, or national origin, be excluded from participation in, be denied the benefits of, or be otherwise subjected to discrimination under any program or activity receiving Federal financial assistance, as required by