Sonora Junction Shoulder Widening Project

This project proposes to widen the existing paved shoulders on US 395 from Burcham Flat Road to the south side of the US 395/SR 108 intersection (postmiles 91.6-93.4). It proposes to install shoulder rumble strips, upgrade existing guardrails, and correct the super-elevations of three substandard curves. There are three “build” alternatives considered for this project. All three alternatives will require realigning Hot Creek at postmile 92.35 to prevent the creek from undermining the highway.

  1. Alternative 1 proposes to widen highway shoulders to 4 ft throughout the project limits.
    • Approximately 400 linear feet of retaining walls will be needed.
    • Non-escalated estimated construction cost $5,053,000.
  2. Alternative 2 proposes to widen the shoulders variably from 4 ft (postmiles 92.4 to 92.9) to 8ft throughout the rest of the project area. This will avoid widening into some portions of Hot Creek.
    • Approximately 900 linear feet of retaining walls will be needed.
    • Cut slopes will be stabilized with anchored wire mesh to reduce rockfall.
    • An estimated 6 culverts will be extended or replaced. Temporary stream diversions will be necessary at these locations.
    • Non-escalated estimated construction cost $9,100,000.
  3. Alternative 3 proposes to widen the highway shoulders to the standard 8ft width.
    • Approximately 1050 linear feet of retaining walls will be needed.
    • Cut slopes will be stabilized with anchored wire mesh to reduce rockfall.
    • At least 6 culverts will be extended or replaced. Temporary stream diversions will be necessary at these locations.
    • Non-escalated estimated construction cost $10,381,000.

Benefits

This project is proposed to enhance roadway safety and make the highway accessible to all modes of transportation. The existing highway shoulders in this area are 2ft wide; standard width is 8ft.

Latest Information

February 1, 2021: Draft Environment Document Ready For Public Comments

The draft environment document for the Sonora Junction Shoulder Widening Project is now available for public review. The public comment period will last from February 1, 2021 through March 8, 2021.

The document can be viewed here: Sonora Junction Shoulders DED

If you'd prefer a printed copy of the document or if you'd like to comment on it, you can do so in one of three ways:

  • Email Angela Calloway
  • Call Angela Calloway at (760) 872-2424
  • Send a letter to: Caltrans District 9, c/o Angela Calloway, 500 South Main Street, Bishop, CA 92514

Project Schedule*

  • February 2021: Draft Environmental Document for Public Comment
  • May 2021: Final Environmental Document and Alternative Chosen
  • Spring/Summer 2024: Begin Construction

*Dates subject to change

Current Status

Caltrans is working on the initial design and environmental assessment phase of the project. Early discussions with regulatory agencies is occurring to define potential environmental impacts and ensure compliance with applicable environmental regulations.

For More Information Contact

Accessibility Assistance: Caltrans makes every attempt to ensure our documents are accessible. Due to variances between assistive technologies, there may be portions of this document which are not accessible. Where documents cannot be made accessible, we are committed to providing alternative access to the content. Should you need additional assistance, please contact us at (916) 654-2852or visithttps://dot.ca.gov/request-ada-compliant-documents.