State Route 2 Pedestrian Improvements Project
Pedestrian Accessibility and Traffic Safety Improvements
Project Updates
Sign up to receive email updates about closures and traffic advisories for the State Route 2 Pedestrian Improvements Project below. If you have already signed up and are receiving project emails, please do not sign up again.
Sign up form: SR-2 Pedestrian Improvements ProjectProject Overview
The project spans 11.5 miles of State Route 2 (SR-2) in the cities of Los Angeles, Glendale and La Cañada Flintridge. The pedestrian facilities at several locations are not in compliance with current Americans with Disabilities (ADA) requirements. This project will improve pedestrian accessibility within State right-of-way by constructing ADA-compliant curb ramps, continental crosswalks and relocating/upgrading Accessible Pedestrian Signals (APS) at the sidewalks for street crossings.
Benefits
The SR-2 Pedestrian Improvements Project will enhance pedestrian pathways and pedestrian infrastructure to make the path of travel accessible, comply with the Americans with Disabilities Act (ADA) regulations and integrate Complete Street Elements. The project also adds safety measures, installing roadside signs and narrowing the traffic lanes by paving delineation, with aims of reducing traffic speed on Angeles Crest Highway (ACH) in La Cañada Flintridge. The total project cost is $14.7 million.
The project spans 11.5 miles of SR-2 from Riverside Drive to Gould Mesa in the cities of Los Angeles, Glendale, and La Cañada Flintridge. Work will take place in 3 segments along SR-2:
- Segment C (Los Angeles, Glendale, La Cañada Flintridge): Riverside Drive to Foothill Boulevard
- Segment D (La Cañada Flintridge) – Route 210 Freeway to La Cañada Arch Canyon Bridge
- Segment E (La Cañada Flintridge.): La Cañada Arch Canyon Bridge to Gould Mesa
KEY ELEMENTS
- ADA upgrades to 59 curb ramps
- Relocating/upgrading 36 Accessible Pedestrian Signals
- 2 new traffic signals
- Installing 1,203 square feet of upgraded Detectable Warning Surfaces
- Installing speed reduction devices along ACH in La Cañada Flintridge, between Route 210 and Gould Mesa
Schedule
Construction is scheduled from fall 2025 through winter 2027/2028.