Guerneville 116 Pedestrian Upgrades

                      Guerneville Pedestrian Upgrades along State Route 116

 

 

Update> February 4, 2026

City streetlights in the eastern portion of town area waiting another inspection by Sonoma County.  There were problems with the original installation, and the contractor has made several changes to comply with regulations.  If the streetlights pass an upcoming inspection by the county they will be switched on.  The contractor also is working on the signal lights at the intersection of River Road and Old River Road at the east end of town. The contractor hopes to have the signal completed by the end of February. 

 

Update> January 20, 2026

Last week the contractor finished work on the traffic signals at the intersection of State Route 116 (Main Street) and Armstrong Woods.  The contractor set out stop signs at the intersection to control traffic, while PG&E de-energized the existing power supply, attached a new upgrade power supply to the signals and activated it.  The new power supply will dramatically improve the reliability and performance of the signals. 

The city streetlights have not yet been reactivated.  The contractor has been working on the streetlight in the eastern part of town since October.  

 

Update> November 18, 2025

As construction winds down to several projects within the project, Caltrans has taken an active interest in removing the telltale signs of construction that are no longer serving much purpose: collecting orange cones, barrels, yellow tape and other remnants of completed construction has restored the natural streetscape of all but a few areas of town. 

 

Update> September 30, 2025

Pretty TreeLast weekend Guerneville hosted its annual Pride Parade. Caltrans remembers the prior year’s parade when work crews arrived in the early morning to remove delineators from the middle of Main Street to provide room for the floats to drive past.

It wasn’t necessary to remove delineators this year, as most of the work has been completed between Mill Street and Armstrong Woods.

Since that time, Caltrans has installed 23 ADA-compliant curb ramps. We have replaced all the sidewalks in town and widened many of them to provide enough width to meet ADA requirements. Caltrans added bulb-outs to Church and Mill Street, and replaced the traffic signals at Armstrong Woods

Caltrans installed two pedestrian beacons (Mills and Church streets) and will activate them later this year.

New Trees to Line the Sidewalks of Guerneville

From a distance the woodchip-filled planter boxes in the sidewalk look like someone tried to fill a gap in the concrete with a sheet of corkboard.

But the situation is temporary.

Sonoma County and the Russian River Chamber of Commerce have plans to plant trees in these beige patches. The type of trees to be planted are under consideration as of this writing.

At right is a picture of a tree in a Guerneville planter box, looking much nicer than an unadorned sheet of corkboard.

 

Update> September 12, 2025

Last weekend Guerneville hosted its annual Pride Parade. Caltrans remembers the prior year’s parade when work crews arrived in the early morning to remove delineators from the middle of Main Street to provide room for the floats to drive past.

It wasn’t necessary to remove delineators this year, as most of the work has been completed between Mill Street and Armstrong Woods.

Since that time, Caltrans has installed 23 ADA-compliant curb ramps. We have replaced all the sidewalks in town and widened many of them to provide enough width to meet ADA requirements. Caltrans added bulb-outs to Church and Mill Street, and replaced the traffic signals at Armstrong Woods

Caltrans installed two pedestrian beacons (Mills and Church streets) and will activate them later this year.

 

Arnstrong WoodsEarlier this week, Caltrans activated the new traffic signal at the intersection of State Route 116 (Main Street) and Armstrong Woods. The signal system is equipped with loop detectors, which detect the presence of vehicles and relay that information to the computerized signal.  Also, Caltrans has timed the signals to correspond with the general traffic patterns at the intersection.

The new signal was a long time coming, and Caltrans appreciates the community's patience, particularly during the temporary signal's initial setup and the wiring connection process, when Caltrans installed temporary stop signs to control the intersection.

Caltrans will next work on the traffic signal at River Road and Main Street and the pedestrian beacons on Main Street at Church and Mill Streets. 

 

Update> August 4, 2025

All sidewalks have been poured. However, some construction items remain. Traffic signals at the intersection of Armstrong Woods and being replaced, and Caltrans will install pedestrian beacons at the intersection of Church and Mill streets. 

 

Update> January 16, 2025

Caltrans has shifted both east - and westbound lanes of Route 116 to the north, creating working room in front of Safeway for sidewalk replacement. The main driveway to Safeway and the Taco Truck, which is parked at the northwest corner of the parking lot, is closed. However, access to both businesses is available by using Church Street. Caltrans has posted "Business Open" signs near the Church Street intersection to advise and remind motorists that Safeway and the Taco Truck can be readily accessed. Work at this location will continue until Monday, January 27, if all goes well.  A spate of bad weather (we've been fortunate so far this month) could cause a delay. Also, unexpected utilities or subsurface tree stumps could hamper progress. 

 

Update> December 2, 2024

Caltrans has finished sidewalk work on a two-block section of eastbound Route 116 between Brookside Lane and Church Street.  Sidewalk work has mostly been completed between Armstrong Woods and Old River Road, except a strip of concrete needs to be removed along the retaining wall that will allow for landscaping.  

Caltrans expects to complete the sidewalk work on westbound Route 116 between Old River Road and Armstrong Woods by the end of January 2025. Likewise, sidewalk work in the westbound direction between Mill Street and Brookside Lane should be completed by January 2025. 

The last section of eastbound Route 116 between Armstrong Woods and Church Street will be completed by summer 2025. 

Caltrans will complete the final section of westbound Route 116 between Armstrong Woods and Mill Street by summer 2025. 

See the image below for a visual rendering of the latest schedule. 

 

Guerneville Update December 2024

 

__________________________________________________

 

Guerneville Pedestrian Upgrades along State Route 116

 

city street

Caltrans began a project in the summer of 2024 to upgrade sidewalks, replace traffic signals and add pedestrian beacons on State Route 116 in Guerneville between River Road and 4th Street.  Some patching of pavement will occur, but this is not a paving project. 

The improvements include replacing 23 curb ramps with ramps compliant with the Americans with Disabilities Act of 1990 (ADA).  

Traffic signals at River Road and Highway 116 will be replaced. The sidewalk between River Road and Armstrong Woods Road will be widened at each light-pole to provide a clearance of 48-inches clearance. Driveways will be reconstructed to conform with the new sidewalks. 

To enhance pedestrian safety, Caltrans will install pedestrian hybrid beacons and curb extensions at intersections of SR-116 at Church and Mill streets.  The new pedestrian signals will be a High-Intensity Activated Cross Walk beacons (HAWK), which will alert motorists to the presence of pedestrians. 

Also, curb extensions or bulb-outs will be installed at several locations to slow down traffic, and to reduce the distance pedestrian must travel to cross the street. 

Being a pedestrian in Guerneville will be a safer, and more pleasant experience by the addition of ADA compliant curb ramps, wider sidewalks, upgraded traffic signals and, curb extensions and pedestrian beacons to accommodate pedestrians at busy intersections on SR-116.

 

Downtown Landscaping, Bike Racks and Other Enhancements

Caltrans worked with Sonoma County PIO to include locally funded landscaping, bike racks, flagpole sleeves, and aesthetic improvements along Main Street.
A new retaining wall at the east end of town, installed to address storm damage, was designed to accommodate murals over 300 feet of wall. Caltrans left an empty swatch of ground between the sidewalk and the wall that can be used for landscaping or other art displays.
Caltrans has replaced three old bike racks and installed 11 new ones, for a total of 14, to provide convenient bike parking throughout downtown.
Caltrans installed 60 flagpole sleeves along Main Street. The County will provide flag poles for use with these sleeves for local celebrations. The sleeves are galvanized to prevent rust, and lids will cover them when not in use.
Caltrans has maintained three existing tree wells and added nine more, bringing the total to 12. The county is currently planting new trees.  
The tree wells are larger than the old ones and provide healthier conditions for new and existing trees, while still leaving enough room to adhere to ADA requirements.
The Fife Creek Bridge includes aesthetic design elements, such as painted bicycle rails that match light poles and railings in the downtown area, and stacked-rock aesthetic bridge ends designed in collaboration with the local art community.
 

 

 

Images and Maps

The images and maps below show examples and diagrams of improvements that will be made along Route 116, including a diagram of a curb extension, an example of an ADA-compliant curb ramp, an image of a pedestrian hybrid beacon and an explanation of its signals, and two maps showing the improvements that will be made during the project.                                                                                                                                                                                                                                                                                             

      Curb Extensions slow traffic and reduce the distance pedestrian must travel to cross the street

ADA Compliant Curb Ramp            

    ADA Curbs with Texture

 

 

 

 

Pedestrian Hybrid Beacon on Sloat Boulevard in San Francisco            Pedestrian Hybrid Signals Explained

 

Exhibit 1 East End                                                                                                                                                                                                                                                                                 

 

Exhibit 2 West End

 

The project also involves upgrading the sidewalks and railings on the Fife Creek Bridge at the west end of town. The ends of the bridge will be detailed with a ledger rock design.

Rendering of Fife Creek Bridge