State Route 9 Saratoga Creek Bridge

History of the Saratoga Creek Bridge Project

A scoping meeting was held on Thursday, April 21, 2016 at the Saratoga Prospect Center. The public comment period for the Scoping Phase concluded on May 20, 2016. Caltrans received feedback from the public and partner agencies during this time that expressed concerns with:

  • maintaining traffic access along SR-9 during construction;
  • The potential visual impacts of the corridor since the project occurs in a section of SR-9 that is a designated scenic highway; and potential impacts to the historical designation of the existing bridge since it is eligible for the National Register of Historic Places.

The project development team took these concerns into consideration in refining the development of the project and settled on the following project alternatives:

  • Alternative 1: Retrofit the Existing Bridge Along Current Alignment (Retrofit Alternative)
  • Alternative 2: Replace Bridge Widening Toward the South of Existing Alignment (Realign Roadway South Alternative)
  • Alternative 3: Replace Bridge Widening Toward the North of Existing Alignment (Realign Roadway North Alternative)
  • Alternative 4: No Build Alternative

The project development team studied the potential impacts of each alternative and circulated a Draft Environmental Impact Report (EIR) under the California Environmental Quality Act and an Environmental Assessment (EA) under the National Environmental Policy Act. The public comment period on the Draft EIR/EA began on February 12, 2018 and ended on March 29, 2018.

A public hearing for the Draft EIR/EA was held on February 28, 2018 in the City of Saratoga. It was an open house format with project development team members available to answer questions about this project and informational display boards. A short presentation was also done to introduce the project to the meeting attendees.

After circulation of the Draft EIR/EA and receipt of comments from the public and reviewing agencies, Caltrans reviewed input and incorporated modifications to the project alternatives that addressed recurrent concerns. Numerous comments on the Draft EIR/EA focused on the duration of construction and the loss of the existing bridge’s historic character. These comments and Caltrans’ response to comments can be found in Appendix K of the Final EIR/EA. Based on the input received, the Project Development Team generated the following two alternatives:

  • Alternative 1.1: Maintain Existing Roadway Alignment with “Hybrid” Bridge (Hybrid Alternative). This alternative is a modified version of Alternative 1 from the Draft EIR/EA. The “Hybrid” Alternative would construct a new bridge within the existing bridge. This maintains much of the original exterior character without modification. The “Hybrid” Alternative would maintain the look and feel of the existing bridge, provide a short construction duration, while also providing the seismic stability required to meet the project’s purpose and need.
  • Alternative 1.2: Maintain Existing Roadway Alignment with New Accelerated Bridge Construction (ABC) Bridge (ABC Alternative). This alternative is a modified version of Alternatives 2 and 3 from the Draft EIR/EA. The ABC Alternative would replace the existing bridge with a new one on the same alignment as the existing bridge. This single-span option would center a new bridge on the existing alignment and provide a short construction duration.

The potential impacts for these alternatives were evaluated and neither alternative introduces new significant impacts not previously discussed in the draft document. Both build alternatives have comparable biological impacts since they both require vegetation clearing in the immediate area around the existing bridge and will install a temporary creek crossing/diversion for Sanborn Creek below the intersection of SR-9 and the creek. Additionally, both build alternatives have an adverse effect on the historic designation of the bridge.

Current Status of the Project

After the public comment period, the Project Development Team applied the selection criteria developed during the scoping phase and refined based on the feedback on the Draft EIR/EA. The team prioritized reducing impacts to traffic, construction duration, and historic resources; while also considering impacts to biological resources, visual resources, and project costs.

The Project Development Team has selected Alternative 1.1 Maintain Existing Roadway Alignment with “Hybrid” Bridge as the preferred alternative for this project. The “Hybrid” Alternative was selected as the preferred alternative because it meets the project’s purpose and need of maintaining safe and stable connectivity along SR-9, while also retaining much of the visual aesthetic of the existing structure by avoiding the concealment or removal of the current bridge’s stone masonry walls. This concern was a recurring public comment during circulation of the Draft EIR/EA.

The “Hybrid” Alternative was found to be more effective at reducing more impacts in the selection criteria compared to the ABC Alternative. There is only one year of construction required to complete the “Hybrid” Alternative, so the duration of traffic impacts is less than the ABC Alternative. The “Hybrid” Alternative also retains the outer, visible, portion of the original stone bridge. While this alternative does not retain the historical standing of the original bridge, it does allow the outer stone masonry walls to remain fully visible.

The Final EIR/EA was approved January 28, 2020 by Caltrans. Caltrans has decided to issue a Finding of No Significant Impact (FONSI) for compliance with NEPA. A Notice of Determination (NOD) was published for compliance with CEQA on February 4, 2020 and a Notice of Availability (NOA) of the FONSI has been sent to the affected units of federal, state, and local government, and to the State Clearinghouse in compliance with EO 12372. The Final EIR/EA and Section 4(f) Evaluation with FONSI can be downloaded here.

Final Environmental Impact Report/ Environmental Assessment and Final Section 4(f) Evaluation with Finding of No Significant Impact