Santa Clara 152 Pavement Rehabilitation Project

(Route 152 CAPM Project)
(Post Miles: 04-SCL-152-PM 7.6/M10.2)

Click Here for The SR-152 Introduction Video

Project display with map and roadway photo

DESCRIPTION:

This fast-tracked project is for pavement rehabilitation and will preserve and extend the life of the existing pavement and improve the ride quality in Santa Clara County in City of Gilroy on Route 152, from 0.3 mile west of Santa Teresa Blvd to Route 101.

PURPOSE & NEED:view of car on road

The purpose of this project is to preserve and extend the life of the existing pavement and improve the ride quality.
The pavement condition within the limits of this project exhibits severe distress with open cracks in some locations, leading to unacceptable ride quality. If left uncorrected, the roadway condition will deteriorate to levels where major roadway rehabilitation might be required.

PROJECT SCOPE:

This project will grind and resurface existing asphalt pavement as well as upgrade traffic signals and existing non-standard ADA curb ramps.

CURRENT STATUS:

  •  Project Initiation Document (PID) was approved on June 2017 and Design was completed on December 2018
  • Advertised on April 2019 and the contract was approved for Granite Construction Company on June 2019
  • This project began construction on September 2019 and is planned to deliver to public by Fall of 2020.

cars at intersection left turn lane