Pavement Rehabilitation

 FACT SHEET

04-Mrn-37- PM R11.2/14.6    EA 2K740
From Ignacio Overhead to Petaluma River Bridge

EA 04-2K740 FactSheet 06302020

Project Description

Rehabilitate of the mainline and ramps pavement within the project limits, correct the existing settlement at PM 13.04, replace metal beam guard rails with Midwest Guardrail systems, and upgrade curb ramps.

Purpose and Need

The purpose of this project is to preserve and extend the life of the existing pavement and improve ride quality. The existing pavement exhibits distress, resulting in poor ride quality and potential pavement failure.

Caltrans Maintenance paved the distressed area every other year in the past few years in order to improve the ride smoothness.

Schedule

Complete Environmental Phase – Fall 2022
Complete Design – Summer 2024
Begin Construction – Winter 2025
End Construction – Summer 2026