Van Ness Avenue Construction Forecast July 14-July 26 2019

Published:

150x100

The following Van Ness Improvement Project construction forecast is subject to change. For more project details, please visit SFMTA.com/VanNess.
 

Tentative schedule:

In the next two weeks crews are scheduled to work on water main installation, sidewalk replacement, restoring the street base, paving, installing a joint-utility trench, installing light poles, street light conduits, and potholing for upcoming work.

The work listed below is scheduled for daytimes, 7:00 a.m. to 8:00 p.m. Planned night work is italicized. The night shift for construction is 8:00 p.m. to 7:00 a.m. During this time, neighbors are advised to anticipate construction-related noise and vibrations as crews work diligently to complete necessary night work.