Tower Fender Replacement Project

Project Facts

Description

Project will remove and replace the existing wood fender system on the Tower Bridge, (Sacramento River Bridge #22-0021) on State Route 275 in West Sacramento.

Project Benefits

Replacing the existing timber fender system with updated materials will ensure that the fender system will continue to protect marine vessels, aid in navigation as applicable, and protect bridge piers.

Funding Breakdown

Local - N/A
State - N/A
Federal - $9.9 million
Estimated Total Project Cost - $9.9 million

Project Schedule

Environmental Document Completed -- January 2016
Right of Way Acquisition Completed -- October 2017
Design Completed -- December 2017
Advertise -- March 2018
Begin Construction -- June 2019
Expected Completion -- November 2020

Partnership

none

Project Contact

Doug Lange, Project Manager
Phone: (530) 741-4465
Email: doug.lange@dot.ca.gov

Dennis Keaton, Public Information Officer
Phone: (530) 741-4574
Email: dennis.keaton@dot.ca.gov

Map

Tower Bridge Fender Map (PDF) 

Documents

Initial Study with Proposed Mitigated Negative Declaration (PDF)
Draft Initial Study with Proposed Mitigated Negative Declaration (2.26 MB PDF)

News / Events

No news available.