The project is funded by the SHOPP 151 Drainage System Restoration program. The project is located on State Route 49 in Nevada County (PM 0.0/7.5) and two locations on SR 49 in Placer County (PM 8.42 & 10.23). The project scope will rehabilitate a total of 22 culverts and 13 corrugated steel pipe (CSP) down drains.

Project Benefits

Purpose: To rehabilitate existing drainage systems showing damage or needing remedial treatments to preserve and extend their service life.

Need: Many of the drainage systems within the project limits are nearing the end of their service life.

Funding Breakdown

This project was programmed in the 2018 SHOPP and will receive construction funding in the 2021-22 fiscal year.

Cost Estimate

Support Cost: $2,313,000
Capital Cost: $2,540,000
Total Project Cost: $4,853,000

Project Schedule

Project Approval & Environmental Document: August 2019
Design Completed: February 2021
Advertise Project: April 2021
Begin Construction: July 2021
Complete Construction: December 2022

Partnership

none

Project Contact

Sam Vandell, Project Manager
Phone: (530) 741-4593

Raquel Borrayo, Public Information Officer
Phone: (530) 701-5209

Map

SR 49 Culvert Rehab Map (PDF) 

Documents

No documents available.

News / Events

No news available.

Video / Photos

No additional photos or videos available.