Sacramento Delta Moveable Bridges Project

Mile Marker, Summer 2019: A Heavy Lift for Movable Bridges

Cost Estimate

Support Cost:  $4,100,000
Capital Cost:  $20,000,000
Total Project Cost:  $24,100,00

Schedule:

Begin Construction:  3/01/19
Complete Construction:  7/29/22

Project Contacts:

Dennis Keaton PIO, (916) 825-5252
Soka Soka Project Manager, (530) 741-5300