State Route 99 Pavement Rehabilitation

Project Facts

Project Description

The project proposes to resurface and restore the pavement on State Route 99 in Merced County from 0.4 mile south of Buhach Overcrossing to 0.8 mile north of West Atwater Overhead. The proposed project would also construct a 1,250 foot-long deceleration lane for the northbound and southbound off-ramp at the Applegate Road interchange. Additional right of way would be required for increased drainage capacity with the construction of five retention basins.

 

Purpose and Need

The purpose of the project is to restore the facility to a state of good repair and to minimize required maintenance. In addition, the project would improve ride quality and extend the service life of the pavement.

 

Funding Source

The project is programmed in the 2016 State Highway Operations and Protection Program (SHOPP) with funding from the 201.122, Pavement Rehabilitation Program.

Project Cost/Programmed

Capital $$ Support $$
Project Approval & Environmental Document $2,223,000
Plans, Specifications, & Estimates $5,200,000
Right of Way $3,369,000 $677,000
Construction $62,340,000 $10,000,000
 Total $65,709,000 $18,100,000

Current Schedule

Date
Approve Project Study Report (M010) July 2014 (Actual)
Project Approval & Environmental Document (M200) December 2017 (Actual)
Right of Way Certification (M410) June 2019 (Actual)
Ready – to – List (M460) June 2019 (Actual)
Approve Construction Contract (M500) December 2019 (Actual)
Project Completion (M600) December 2022

 

Project Status

Construction began in spring 2020.

 

Contact Information

Caltrans District 10 - Public Information Office

Phone: (209) 948-7977

Email: district10publicaffairs@dot.ca.gov.

Address:  P.O. Box 2048, Stockton, CA 95201-2048