Pedestrian Hybrid Beacon System State Route 108 Project

Project Description

Install Pedestrian Hybrid Beacon (PHB) System at the intersection of State Route 108 and Stanislaus Avenue/South Wood Avenue in the City of Oakdale in Stanislaus County.

project map

Project Benefits

Purpose

The purpose of this project is to improve pedestrian safety at the existing marked crosswalk.

Need

The need is to alert inattentive drivers to stop for pedestrians entering the crosswalk.


Current Schedule

Project Approval & Environmental Document (M200)

Winter 2025

Right of Way Certification (M410)

Winter 2026

Ready to List (M460)

Winter 2026

Approved Construction Contract (M500)

Summer 2026

Project Completion (M600)

Fall 2026


Funding Source


This project will be funded through the Minor A Program.


Project Status


This project is currently in Environmental Documents (PA&ED) phase.


Project Cost/Programmed (x$1,000):

Programed Project Cost Capital $ Support $
Project Approval & Environmental Document   $723
Plans, Specifications, & Estimates   $1025
Right of Way $47 $118
Construction $1,024 $598
Projected Cost as of May 2, 2024: Planned $ Expended $
Project Approval & Environmental Document $723 $430
Plans, Specifications, & Estimates $1025 $42
Right of Way $118 $0
Construction $598 $0

Project Manager

Mohamed Khairan

Mohamed Khairan
Office Cell: (209) 639-6328
Email: Mohamed.Khairan@dot.ca.gov

Public Information Office

District 10 logo

Phone: (209) 948-7977
Email: District10PublicAffairs@dot.ca.gov
Address: P.O. Box 2048, Stockton, CA 95201-2048