Interstate 580 / Corral Hollow Road Interchange Project

Project Description

In coordination with the California Department of Transportation, the City of Tracy proposes to improve the Interstate 580 I-580/Corral Hollow Road Interchange to enhance local and regional circulation, support the efficient movement of goods, and reduce existing and future congestion. A Diverging Diamond Interchange (DDI) is the Build Alternative. Corral Hollow Road would be widened to four lanes from two lanes and the on and off-ramps would be widened to three lanes from the current single lane. Bike lanes and sidewalks are also built through the interchange.

I-580 Corral Hollow Road Interchange Project Map Image

Project Benefits

Purpose

Implement operational enhancements to accommodate the expected increase in traffic from ongoing developments. Improve bicycle and pedestrian access on Corral Hollow Road at the interchange. Enhance traffic flow and mobility for vehicles, bicycles, and pedestrians. Strengthen connectivity for residents, businesses, and regional travelers while minimizing traffic delays and improving overall roadway functionality.

Need

The current interchange is insufficient to handle future traffic demands and provide easy access. The project area also lacks multimodal access and connectivity. To improve this, sidewalks and bike lanes are needed through the interchange to link the existing facilities on both the north and south sides of the Corral Hollow Road.


Current Schedule

Fall 2026

Project Study Report (M010)

Fall 2026

Project Approval & Environmental Document (M200)

Spring 2028

Right of Way Certification (M410)

Spring 2028

Ready to List (M460)

Fall 2028

Approved Construction Contract (M500)

Summer 2030

Project Completion (M600)


Documents

Initial Study with Proposed Mitigated Negative Declaration - PDF (1190 KB)

Notice of Intent to Adopt an Initial Study with Proposed Mitigated Negative Declaration


Funding Source


The City of Tracy's Local funds and Federal-aid funds will fund the project. 40.XX.400.000


Project Status


Project is currently in K Phase. The draft environmental document was approved on 6/26/29. The draft PSR-PR is anticipated to be approved in early July 2026. Final environmental approval is scheduled for late August/early September 2026.


Project Cost/Programmed (x$1,000):

Programed Project Cost Capital $ Support $
Project Approval & Environmental Document   $2,900
Plans, Specifications, & Estimates   $5,360
Right of Way $2,536 $225
Construction $56,852 $7,600
Projected Cost as of June 29, 2026: Planned $ Expended $
Project Approval & Environmental Document $2,900 $0
Plans, Specifications, & Estimates $5,360 $0
Right of Way $225 $0
Construction $7,600 $0

Project Manager

Bairong Yu

Bairong Yu
Office Cell: (209) 983-7721
Email: Bairong.Yu@dot.ca.gov

Public Information Office

District 10 logo

Phone: (209) 948-7977
Email: District10PublicAffairs@dot.ca.gov
Address: P.O. Box 2048, Stockton, CA 95201-2048