Calaveras State Route 4 ADA Improvements Project

Project Description

This project proposes building approximately 1,100 feet of sidewalk, seven ADA curb ramps, and crosswalks in Murphys along westbound State Route 4 (SR 4) from Pennsylvania Gulch Road to Main Street, and along eastbound Pennsylvania Gulch Road from the SR 4 intersection to Albert Michelson Elementary School. The project also includes a HAWK (High intensity Activated crossWalK) system at the SR 4 and Pennsylvania Gulch Road intersection.

Calaveras State Route 4 ADA Improvements Project Map

Project Benefits

Purpose

The purpose is to build the sidewalks and crosswalk to enhance safety for all non-motorized users.

Need

There’s a need to close a critical gap and help connect the local elementary school and community park isolated on the corner of Pennsylvania Gulch Road to the rest of the town.


Current Schedule

Winter 2023 (A)

Project Approval & Environmental Document (M200)

Winter 25/26 (A)

Ready to List (M460)

Summer 26 (T)

Approved Construction Contract (M500)

Spring 2027 (T)

Project Completion (M600)

Spring 2028 (T)

Final Report (M700)

Fall 2028 (T)

End Project (M800)

Summer 2029 (T)

Final Project Closeout (M900)


Funding Source


This project is programmed as a SHOPP Minor A with funding from 201.400 with an aditional funding program, Highway Safety Improvement Program (HSIP).


Project Status


Project currently in PS&E Phase.


Project Cost/Programmed (x$1,000):

Programed Project Cost Capital $ Support $
Project Approval & Environmental Document   $518
Plans, Specifications, & Estimates   $1,200
Right of Way $207 $140
Construction $1,600 $1,088
Projected Cost as of February 3, 2026: Planned $ Expended $
Project Approval & Environmental Document $518 $457
Plans, Specifications, & Estimates $1,200 $1,668
Right of Way $140 $76
Construction $1,088 $0

Public Information Office

District 10 logo

Phone: (209) 948-7977
Email: District10PublicAffairs@dot.ca.gov