State Route 4 Wagon Trail Realignment Project
Project Description
The project is located between the town of Copperopolis and the City of Angels Camp in Calaveras County. The Eastern Segment of the SR 4 Wagon Trail Realignment Project consists of constructing SR 4 on a new alignment between Stallion Way and approximately 1.6 miles west of the State Route 4 /49 Junction near Stockton Rd.

Project Benefits
Purpose and Need
Reduce travel delay and improve safety on SR 4 between Copperopolis and Angels Camp. Project benefits will be improved traffic mobility, improved traffic safety, reduced congestion, and related improvements to Level of Service.
Current Schedule
Winter 2017 (A)
Project Approval & Env. Doc. (M200)
Winter 2025 (A)
Begin Design (M210)
Summer 2028 (T)
Right of Way Certification (M410)
Summer 2028 (T)
Ready to List (M460)
Fall 2028 (T)
Approve Construction Contract (M500)
Summer 2030 (T)
Project Completion (M600)
Funding Source
The project is funded through a combination of Regional Improvement Program (RIP), Trade Corridors Enhancement Program, and local funds.
Project Status
Survey has been completed. Design is currently finalizing the project alignment. Environmental will begin revalidation technical studies in March, and Right of Way is anticipated to start the appraisal process in June 2026.
Project Cost/Programmed (x$1,000):
| Programed Project Cost | Capital $ | Support $ |
|---|---|---|
| Project Approval & Environmental Document | N/A | N/A |
| Plans, Specifications, & Estimates | $0 | $4,500 |
| Right of Way | $7,500 | $1,042 |
| Construction | $2,958 | $8,324 |
| Projected Cost as of June, 2026: | Planned $ | Expended $ |
|---|---|---|
| Project Approval & Environmental Document | N/A | N/A |
| Plans, Specifications, & Estimates | $4,500 | $706 |
| Right of Way | $1,042 | $255 |
| Construction | TBD | TBD |