Plymouth Gateway & Trails Project
Project Description
The project proposes to install 3,543 linear feet (LF) of a paved Class 1 trail along SR 49 from about 1,050 LF north of Zinfandel Parkway to 300 LF south of the Main Street, Plymouth, CA. The gateway signs were removed from the original Clean CA Enhancement Proposal (CCEP). The local community leaders engaged in the project proposed the trail system was the highest priority to them.
Project Benefits
Purpose
The purpose of this project is to provide a Class 1 Bicycle and Pedestrian trail to enhance livability, recreation and safety for the community and visitors. The trail is a first step toward beautifying the State Route 49.
Need
There is a need for trail to provide recreational opportunities along the highway to promote health and safety.
Current Schedule
Winter 2022 (A)
Program Project (M015)
Fall 2023 (A)
Project Approval & Environmental Document (M200)
Summer 2023 (A)
Right of Way Certification (M410)
Spring 2024 (A)
Ready to List (M460)
Fall 2024 (A)
Approved Construction Contract (M500)
Summer 2025 (T)
Project Completion (M600)
Fall 2025 (T)
End Project (M800)
Funding Source
This project is programmed as a Clean California project with funding from 800.200.
Project Status
Contract approved on 10/18/24.
Project Cost/Programmed (x$1,000):
Programed Project Cost | Capital $ | Support $ |
---|---|---|
Project Approval & Environmental Document | $0 | $125 |
Plans, Specifications, & Estimates | $0 | $605 |
Right of Way | $0 | $5 |
Construction | $1,309 | $60 |
Projected Cost as of February 26, 2025: | Planned $ | Expended $ |
---|---|---|
Project Approval & Environmental Document | $125 | $117 |
Plans, Specifications, & Estimates | $605 | $653 |
Right of Way | $5 | $1 |
Construction | $60 | $8 |