Tuolumne 49 Pavement Anchor Project

Project Description

This project proposes to restore the pavement from Jamestown to Sonora while adding and installing complete street assets within the project limits along with addressing culvert and bridge work in Sonora. The work consists of cold planning existing pavement and resurfacing with various materials while adding/installing sidewalks, Class I & II bike lanes, transit stops, rehabilitation of culvert and a retaining wall. The bridge work includes placing polyester concrete on bridge deck and approach slabs.

10-1P090 Tuolumne 49 Pavement Anchor Project Map

Project Benefits

Purpose & Need

The purpose of the project is to rehabilitate and extend pavement service life, repair infrastructure, provide pedestrian and bicyclist facilities, and improve access to public transit. The project is needed to rehabilitate deteriorating pavement along SR 49, provide pedestrian, bicyclist, and transit facilities within Jamestown, upgrade curb ramps to comply with ADA requirements and rehabilitate and replace culverts. There is also a need to rehabilitate deteriorating bridge deck at Mono Way Undercrossing and to widen Woods Creek Bridge to accommodate evacuation traffic as well as provide safe pedestrian and bicycle facilities.


Current Schedule

Summer 2023 (A)

Approve Planning Document

Fall 2026 (T)

Complete Environmental Phase

Winter 2029

Right Of Way Certification

Spring 2030

Advertise

Summer 2030

Begin Construction

Winter 2032

End Construction


Funding Source


2024 SHOPP Cycle. Program: 20.10.201.121 Pavement Preservation – DIB 81. 201.119 Bridge Preservation, and 201.361 ADA Pedestrian Infrastructure.


Project Status


Draft environmental document in scheduled to be completed in July 2026. Project team is working on draft project report


Project Cost/Programmed (x$1,000):

Programed Project Cost Capital $ Support $
Project Approval & Environmental Document   $3,499
Plans, Specifications, & Estimates   $3,047
Right of Way $2,726 $3,160
Construction $46,901 $6,151
Projected Cost as of June 4, 2026: Planned $ Expended $
Project Approval & Environmental Document $3,499 $3,383
Plans, Specifications, & Estimates $3,047 $0
Right of Way $3,160 $0
Construction $6,151 $0

Project Manager

Bairong Yu

Bairong Yu
Office Cell: (209) 983-7721
Email: Bairon.Yu@dot.ca.gov

Public Information Office

District 10 logo

Phone: (209) 948-7977
Email: District10PublicAffairs@dot.ca.gov
Address: P.O. Box 2048, Stockton, CA 95201-2048