Calaveras State Route 4 Pavement Rehabilitation Project
Project Description
This project proposes to restore, rehabilitate, and replace pavement and roadway facilities on State Route (SR) 49 in Calaveras County from the Tuolumne County line at post mile R0.0 to the Amador County line at post mile 30.87. The project passes through the communities of Angels Camp, San Andreas, and Mokelumne Hill and will improve pavement service life and ride quality while addressing non-standard roadway facilities.
The scope includes cold planing and overlay, repairing failed pavement and dig-outs, repaving gores, pullouts and a vista point, restriping, upgrading guardrail systems, replacing signs and dikes, rehabilitating drainage systems, replacing loop detectors, and constructing a concrete bridge structure beneath the roadway near PM R21.0 to stabilize and reinforce weak underlying roadway materials.

Project Benefits
Purpose and Need
The purpose of the project is to restore and replace pavement and roadway facilities to current operational standards to improve serviceability, maintenance costs, and ride quality within the project limits. The project is needed because pavement structural distress identified in the 2021 Automated Pavement Condition Survey is causing multiple roadway facilities to deteriorate and perform below capacity, resulting in lower ride quality and increased maintenance service and costs.
Current Schedule
07/01/2026
Project Program (M015)
09/11/2026
Begin Environmental (M020)
04/16/2029
Approve Final Environmental Document (M160)
05/31/2029
Project Approval & Environmental Document (M200)
07/01/2030
Right of Way Certification (M410)
12/30/2030
Ready to List (M460)
07/28/2031
Approved Construction Contract (M500)
12/31/2033
Project Completion (M600)
06/27/2036
End Project (M800)
Funding Source
The project is eligible for Federal-aid funding and is a candidate for the 2026 State Highway Operation and Protection Program (SHOPP), Pavement Program (20.10.201.121), with a target delivery fiscal year of 2030/31.
Project Status
The Project Initiation Report was approved on June 27, 2025. The project is identified as a long-lead SHOPP project candidate, with programming targeted for July 2026 and delivery in the 2030/31 fiscal year. PA&ED will include development of the environmental document and necessary technical studies, with coordination anticipated for biological, cultural, water quality, drainage, right-of-way, and other project requirements.
Project Cost/Programmed (x$1,000):
| Programed Project Cost | Capital $ | Support $ |
|---|---|---|
| Project Approval & Environmental Document | $4,820 | |
| Plans, Specifications, & Estimates | $4,640 | |
| Right of Way | $589 | $380 |
| Construction | $46,110 | $9,760 |