Interstate 5 Matthews Road Intersection Improvements

Project Description

The proposed I-5/Mathews Rd Intersection Improvements project is located in French Camp, San Joaquin County, on I-5 at the Mathews Road interchange. The project proposes to install interconnected signals at four intersections, modify sidewalks to meet Americans with Disabilities Act (ADA) standards, and modify turn lanes to accommodate Surface Transportation Assistance Act (STAA) trucks and projected traffic volumes. Modifications will be performed at the following intersections:

  • Two Northbound (NB) and Southbound (SB) ramp intersections at I-5/Mathews Rd
  • Two County intersections at Mathews Rd/Manthey Rd and Mathews Rd/El Dorado St

project map

Project Benefits

Purpose

The purpose of this project is to mitigate the traffic impacts associated with the development and opening of the Veterans Administration (VA) community-based outpatient clinic and living center in the French Camp area of San Joaquin County by signalizing the following intersections as mentioned above.

Need

Traffic Impact Study (TIS), completed by W-Trans on July 12, 2019, showed that the VA project would result in significant impacts at the following three intersections: Mathews Rd/Manthey Rd, Mathews Rd/I-5 SB Off-ramp, and Mathews Rd/I-5 NB Off-ramp. The impacts would significantly increase the queue lengths at the I-5 NB & SB Off-ramps, with queues projected to extend past the off-ramp gore point and onto the freeway mainline. In addition, the improvement of a fourth intersection at Mathews Rd/El Dorado St is necessary, due to its proximity and the need for it to be a part of the coordinated signal system to reduce queueing that would otherwise affect the overall traffic operations.


Current Schedule

May 2023 (A)

Project Study Report Completed

May 2023 (A)

Begin Design

May 2024 (A)

Interim Installed

Feburary 2026 (A)

End Design

April 2026 (A)

Project Advertised

June 2026 (T)

Award Contract

July 2026 (T)

Begin Construction

August 2027 (T)

End Construction


Funding Source


The project is sponsored by the Department of Veteran Affairs (VA) under the VA Appropriations for Major Construction from the Veterans Health Administration (VHA) National Capital Assets Realignment for Enhanced Services (CARES) Plan.


Project Status


Construction contract was advertised in April 2026. Bids were opened and the contract is scheduled to be awarded in June 2026.


Project Cost/Programmed (x$1,000):

Programed Project Cost Capital $ Support $
Project Approval & Environmental Document   $0
Plans, Specifications, & Estimates   $2,484
Right of Way $908 $475
Construction $9,540 $1,075
Projected Cost as of April 16, 2025: Planned $ Expended $
Project Approval & Environmental Document $0 $0
Plans, Specifications, & Estimates $2,484 $2,460
Right of Way $475 $377
Construction $1,057 $0

Project Manager

Sridhar Kidambi

Sridhar Kidambi
Office Cell: (209) 986-1223
Email: Sridhar.Kidambi@dot.ca.gov

Public Information Office

District 10 logo

Phone: (209) 948-7977
Email: District10PublicAffairs@dot.ca.gov
Address: P.O. Box 2048, Stockton, CA 95201-2048