State Route 49 Angels Camp Complete Streets

Project Description

Install/Upgrade curb ramps, sidewalks, driveways, and accessible pedestrian signal to current American with Disabilities Act (ADA) standards.

State Route 49 Angels Camp Upgrade Project Map

Project Benefits

Purpose and Need

The purpose of the project is to upgrade the pedestrian facilities to current ADA standards to improve pedestrian mobility and accessibility. The need of the project is to access barriers to pedestrians with disabilities existing within the project location. As identified in the Statewide ADA Transition Plan, the access barriers include non-ADA compliant curb ramps, sidewalks, driveways and pedestrian push buttons.

This project is also funded with Complete Streets Reservation funds. Extensive coordination with the City of Angels Camp has resulted in creating a project that meets the community needs and long-term goals. The additional funds will provide additional sidewalks to close off gaps in pedestrian infrastructure within the project limits, add street lighting, planting, designated bike lane striping, and wayfinding signs to the historic downtown.


Current Schedule

Summer 2019 (A)

Project Study Report (M010)

Fall 2021 (A)

Project Approval & Environmental Document (M200)

Summer 2024 (A)

Right of Way Certification (M410)

Summer 2024 (A)

Ready to List (M460)

Summer 2025 (A)

Approved Construction Contract (M500)

Summer 2028 (T)

Project Completion (M600)


Funding Source


20.XX.201.361


Project Status


  • Project is currently in the Construction & Right of Way phases.
  • Pre-construction meeting was held in July 2025 and construction is underway.

Project Cost/Programmed (x$1,000):

Programed Project Cost Capital $ Support $
Project Approval & Environmental Document   $1,417
Plans, Specifications, & Estimates   $2,070
Right of Way $471 $2,158
Construction $7,858 $1,400
Projected Cost as of October 2nd, 2025: Planned $ Expended $
Project Approval & Environmental Document $1,417 $1,199
Plans, Specifications, & Estimates $2,070 $2,040
Right of Way $2,158 $1,384
Construction $1,400 $174

Project Manager

Haqiqat Kalirao

Haqiqat Kalirao
Office Cell: (209) 986-9536
Email: Haqiqat.Kalirao@dot.ca.gov

Public Information Office

District 10 logo

Phone: (209) 948-7977
Email: District10PublicAffairs@dot.ca.gov
Address: P.O. Box 2048, Stockton, CA 95201-2048