State Route 4 Hoods Creek Bridge Replacement Project

Project Description

The proposed project is located in Stanislaus County on State Route (SR) 4 at Hoods Creek Bridge (#38-0041) at PM 7.28. This project proposes to remove and replace the existing Hoods Creek Bridge. The proposed bridge will be widened to accommodate standard 8-foot (ft) shoulders and the profile of the bridge will be raised. There is one build alternative and the No Build alternative. Temporary Construction Easements (TCE) will be necessary for construction and staging purposes.

Image of Hoods Creek Bridge Replacement Project Map

Project Benefits

Purpose

The purpose of this project is to improve the structural integrity and address the nonstandard condition of Hoods Creek Bridge (Bridge Number 38-0041) on State Route 4.

Need

The project is needed due to the poor structural integrity, excessive bridge scouring, recurring flooding, and nonstandard conditions of Hoods Creek Bridge, as identified in the Structure Maintenance and Investigations Bridge Inspection Report dated March 4, 2020.


Current Schedule

Summer 2021(A)

Project Study Report (M010)

Spring 2026

Project Approval & Environmental Document (M200)

Summer 2028

Right of Way Certification (M410)

Summer 2028

Ready to List (M460)

Spring 2029

Approved Construction Contract (M500)

Spring 2030

Project Completion (M600)


Documents

Initial Study with Proposed Mitigated Negative Declaration Volume 1 of 2 - January 2026 (PDF) 1,530 KB


Funding Source


20.XX.201.111 (Bridge Scour)
This project is amended into the 2024 State Highway Operations and Protection Program (SHOPP) with Bridge Scour Mitigation as the primary objective for construction in the 2028/29 fiscal year.


Project Status


In PA&ED. Environmental studies are ongoing.


Project Cost/Programmed (x$1,000):

Programed Project Cost Capital $ Support $
Project Approval & Environmental Document   $2,378
Plans, Specifications, & Estimates   $2,511
Right of Way $2,040 $505
Construction $9,282 $3,493
Projected Cost as of January 8, 2026: Planned $ Expended $
Project Approval & Environmental Document $2,378 $2,020
Plans, Specifications, & Estimates $2,438 $0
Right of Way $490 $0
Construction $3,391 $0

Project Manager

Mo Khairan

Mo Khairan
Office Cell: (209) 639-6328
Email: Mohamed.Khairan@dot.ca.gov

Public Information Office

District 10 logo

Phone: (209) 948-7977
Email: District10PublicAffairs@dot.ca.gov