State Route 4 Transportation Management Systems Upgrade
Project Description
The California Department of Transportation (Caltrans) proposes to improve the mobility of travelers on State Routes 4, 12, 26, 33, 88, 99, and 120, Interstate 5, and Interstate 205 by updating Transportation Management System elements at 37 locations across San Joaquin County that are obsolete or do not meet current Caltrans standards. The project would also install new fiber-optic cables at eight locations, upgrade or install traffic monitoring stations in cabinets at nine locations, install weather information systems at six locations, install pull boxes at six locations, install a sewer hole at one location, upgrade motor vehicle pullouts at four locations, and replace or install closed-circuit television cameras at 25 locations.
Project Benefits
Purpose
The purpose of the project is to improve the mobility of travelers on State Routes 4, 12, 26, 33, 88, 99, and 120, Interstate 5, and Interstate 205 by updating Transportation Management System elements at 37 locations across San Joaquin County.
Need
The project is needed because Transportation Management System elements in the project area were identified as being obsolete or not meeting current Caltrans standards.
Funding Source
Transportation Management
Project Cost/Programmed
Programed Project Cost | Capital $ | Support $ |
---|---|---|
Project Approval & Environmental Document | $0 | $962,000 |
Plans, Specifications, & Estimates | $0 | $1,436,000 |
Right of Way | $25,000 | $158,000 |
Construction | $9,990,000 | $1,559,000 |
Projected Cost as of (December 30, 2022) | Planned $ | Expended $ |
---|---|---|
Project Approval & Environmental Document | $962,000 | $675,000 |
Plans, Specifications, & Estimates | $1,436,000 | $0 |
Right of Way | $158,000 | $0 |
Construction | $1,559,000 | $0 |
Current Schedule
Process | Date |
---|---|
Project Study Report (M010) | Spring 2018 |
Project Approval & Environmental Document (M200) | 1/25/2023 (Actual) |
Right of Way Certification (M410) | Winter 2024 |
Ready to List (M460) | Spring 2024 |
Approved Construction Contract (M500) | Fall 2024 |
Project Completion (M600) | Summer 2025 |
Project Status
This project is currently in PA&ED Phase.
Project Contact
Caltrans District 10 - Public Information Office
Phone: (209) 948-7977
Email: district10publicaffairs@dot.ca.gov
Documents
Initial Study with Mitigated Negative Declaration - FINAL - January 2023 (PDF 1.1 MB)
Title VI Information
The California Department of Transportation (Caltrans) assures that no person shall, on the basis of race, color, or national origin, be excluded from participation in, be denied the benefits of, or be otherwise subjected to discrimination under any program or activity receiving Federal financial assistance, as required by Title VI of the Civil Rights Act of 1964, as amended, the Civil Rights Restoration Act of 1987, and Federal Executive Order 12898 (Federal Actions to Address Environmental Justice in Minority Populations and Low-Income Populations).
Caltrans will make every effort to ensure nondiscrimination in all of its programs and activities, whether they are federally funded or not, and that services and benefits are fairly distributed to all people, regardless of race, color, or national origin. In addition, Caltrans will facilitate meaningful participation in the transportation planning process in a nondiscriminatory manner.