Interstate 5 Pavement Anchor Project
Project Description
This Pavement Anchor Project proposes to rehabilitate Interstate 5 (I-5) in and near the City of Stockton, San Joaquin County from Hammer Lane undercrossing (UC) (PM 32.5) to the Sacramento County line (PM 49.8).
The proposed scope of work incorporates 9 satellite assets that includes guardrail upgrade, bridge rail replacement, culvert replacement, operational improvements, sign replacements, Transportation Management System (TMS) elements, roadside safety improvements, lighting, and American with Disabilities Act (ADA) improvements.
The proposed pavement strategy is to replace the existing pavement with Continuously Reinforced Concrete Pavement (CRCP) and Joint Plain Concrete Pavement (JPCP) on the outside shoulder in both the northbound and southbound directions from Hammer Lane UC to Eight Mile Road UC. There are five bridges between Hammer Lane UC and Eight Mile Road UC. The approach slabs through this section will also be replaced. The pavement for the remainder of the project limits will be addressed with individual slab replacement using Rapid Strength Concrete (RSC) in various locations along I-5 with diamond grinding to meet smoothness requirements across all lanes in both the northbound and southbound directions from Eight Mile Rd (PM 35.5) to the Sacramento County line (PM 49.8). The ramps within the project limits are proposed to be cold planed 0.25 feet and overlaid with 0.25 feet HMA.
Project Benefits
Purpose and Need
The purpose of this project is to rehabilitate and extend the pavement service life, repair the infrastructure, and improve mobility on I-5 in San Joaquin County, in and near the city of Stockton from Hammer Lane Undercrossing to the Sacramento County line.
Funding Source
The total estimated cost of the project at completion is $123,378,000. The project was programed in the 2020 State Highway Operation Protection Program (SHOPP) cycle under the Pavement Resurfacing, Restoring, Rehabilitation (3R) Program (funding code 201.120) for delivery in the 22/23 fiscal year.
Project Cost/Programmed
Programed Project Cost (x$1,000) | Capital $ | Support $ |
---|---|---|
Project Approval & Environmental Document | $0 | $2,108 |
Plans, Specifications, & Estimates | $0 | $4,153 |
Right of Way | $69 | $162 |
Construction | $106,733 | $10,953 |
Projected Cost as of April 24, 2024 | Planned $ | Expended $ |
---|---|---|
Project Approval & Environmental Document | $2,108 | $1,684 |
Plans, Specifications, & Estimates | $4,153 | $4,070 |
Right of Way Support | $162 | $154 |
Construction Support | $10,953 | $86 |
Right of Way Capital | $69 | $0 |
Construction Capital | $111,680 | $0 |
Current Schedule
Project Initiation Report (M010) | 6/17/2019 (A) |
Project Approval & Environmental Document (M200) | 1/26/2022 (A) |
Right of Way Certification (M410) | 5/18/2023 (A) |
Ready to List (M460) | 6/26/2023 (A) |
Approve Construction Contract (M500) | 03/08/2024 (A) |
Contract Completion (M600) | 11/20/2026 |
Project Status
The project was advertised on 9/18/2023 and was awarded on 1/12/24 and approved on 03/21/24. Construction operations are anticipated to begin in June 2024.
Project Contact
Caltrans District 10 - Program Project Management
Tarek Chowdhury, Project Manager
Phone: (209) 693-3405
Email: tarek.chowdhury@dot.ca.gov
Caltrans District 10 - Public Information Office
Phone: (209) 948-7977
Email: district10publicaffairs@dot.ca.gov
Address: P.O. Box 2048, Stockton, CA 95201-2048
Title VI Information
The California Department of Transportation (Caltrans) assures that no person shall, on the basis of race, color, or national origin, be excluded from participation in, be denied the benefits of, or be otherwise subjected to discrimination under any program or activity receiving Federal financial assistance, as required by Title VI of the Civil Rights Act of 1964, as amended, the Civil Rights Restoration Act of 1987, and Federal Executive Order 12898 (Federal Actions to Address Environmental Justice in Minority Populations and Low-Income Populations).
Caltrans will make every effort to ensure nondiscrimination in all of its programs and activities, whether they are federally funded or not, and that services and benefits are fairly distributed to all people, regardless of race, color, or national origin. In addition, Caltrans will facilitate meaningful participation in the transportation planning process in a nondiscriminatory manner.