Interstate 5 Pavement Anchor Project
Project Description
This Pavement Anchor Project proposes to rehabilitate Interstate 5 (I-5) in and near the City of Stockton, San Joaquin County from Hammer Lane undercrossing (UC) (PM 32.5) to the Sacramento County line (PM 49.8).
The proposed scope of work incorporates 9 satellite assets that includes guardrail upgrade, bridge rail replacement, culvert replacement, operational improvements, sign replacements, Transportation Management System (TMS) elements, roadside safety improvements, lighting, and American with Disabilities Act (ADA) improvements.
The proposed pavement strategy is to replace the existing pavement with Continuously Reinforced Concrete Pavement (CRCP) and Joint Plain Concrete Pavement (JPCP) on the outside shoulder in both the northbound and southbound directions from Hammer Lane UC to Eight Mile Road UC. There are five bridges between Hammer Lane UC and Eight Mile Road UC. The approach slabs through this section will also be replaced. The pavement for the remainder of the project limits will be addressed with individual slab replacement using Rapid Strength Concrete (RSC) in various locations along I-5 with diamond grinding to meet smoothness requirements across all lanes in both the northbound and southbound directions from Eight Mile Rd (PM 35.5) to the Sacramento County line (PM 49.8). The ramps within the project limits are proposed to be cold planed 0.25 feet and overlaid with 0.25 feet HMA.
Project Benefits
Purpose and Need
The purpose of this project is to rehabilitate and extend the pavement service life, repair the infrastructure, and improve mobility on I-5 in San Joaquin County, in and near the city of Stockton from Hammer Lane Undercrossing to the Sacramento County line.
Current Schedule
Project Study Report (M010)
6/17/2019 (A)
Project Approval & Environmental Document (M200)
1/26/2022 (A)
Right of Way Certification (M410)
5/18/2023 (A)
Ready to List (M460)
6/26/2023 (A)
Approved Construction Contract (M500)
03/08/2024 (A)
Project Completion (M600)
11/20/2026








Funding Source
The total estimated cost of the project at completion is $123,378,000. The project was programed in the 2020 State Highway Operation Protection Program (SHOPP) cycle under the Pavement Resurfacing, Restoring, Rehabilitation (3R) Program (funding code 201.120) for delivery in the 22/23 fiscal year.
Project Status
The project was advertised on 9/18/2023 and was awarded on 1/12/24 and approved on 03/21/24. Construction operations are anticipated to begin in June 2024.
Project Cost/Programmed (x$1,000):
Programed Project Cost | Capital $ | Support $ |
---|---|---|
Project Approval & Environmental Document | $0 | $2,108 |
Plans, Specifications, & Estimates | $0 | $4,153 |
Right of Way | $69 | $162 |
Construction | $106,733 | $10,953 |
Projected Cost as of April 24, 2024: | Planned $ | Expended $ |
---|---|---|
Project Approval & Environmental Document | $2,108 | $1,684 |
Plans, Specifications, & Estimates | $4,153 | $4,070 |
Right of Way Support | $162 | $154 |
Construction Support | $10,953 | $86 |
Right of Way Capital | $69 | $0 |
Construction Capital | $111,680 | $0 |
Public Information Office

Phone: (209) 948-7977
Email: District10PublicAffairs@dot.ca.gov
Address: P.O. Box 2048, Stockton, CA 95201-2048