State Route 4 Capital Maintenance

SJ4 CAPM Banner

Project Description

This project proposes to repair localized areas of pavement failure and place a Rubberized Hot Mix Asphalt overlay. The project limits are on State Route (SR) 4 from Golden Gate Avenue Overcrossing at SR 99 in the City of Stockton in San Joaquin County to 0.5 mile east of Dunton Road in Telegraph City in Stanislaus County.

The scope of work also includes rehabilitating culverts; removing and replacing bridge railing; overlay bridges decks; upgrading and/or installing warning signs; removing and upgrading guardrails, rumble strips, traffic stripes and dikes; placing shoulder backing and installing Maintenance Vehicle Pullout (MVP).

Sj4 CAPM Location Map

Project Benefits

Purpose and Need

The purpose of this project is to address pavement, bridge, drainage and warning sign needs on SR 4. The need is to extend the service life of pavement; replace existing bridge railings at seven bridges with railings that meet current standards; rehabilitate 21 culverts to avoid possible flooding or settlement of the roadway; upgrade driveways, rumble trips, traffic stripes, warning signs to current standards; upgrade existing guardrails to Midwest Guardrail System, and install MVP to facilitate highway maintenance.


Current Schedule

Summer 2017 (Actual)

Project Study Report (M010)

Spring 2023

Project Approval & Environmental Document (M200)

Summer 2024

Right of Way Certification (M410)

Summer 2025

Ready to List (M460)

Fall 2026

Approved Construction Contract (M500)

Winter 2028

Project Completion (M600)


Funding Source


The project was programmed in the 2020 State Highway Operations and Protection Program (SHOPP) with funding from the 201.121, Pavement Preservation Program.


Project Status


Project has been advertised, however due to bidder inquiries, an addendum is being created which may delay the project bid opening. Planned bid opening was 9/25/2025 and could be delayed as much as 6 months.


Project Cost/Programmed (x$1,000):

Programed Project Cost Capital $ Support $
Project Approval & Environmental Document   $2,660
Plans, Specifications, & Estimates   $2,701
Right of Way $379 $657
Construction $36,437 $5,250
Total $36,816 $11,268

Project Manager

Jim Benton

Jim Benton
Office Cell: (209) 693-3405
Email: Jim.Benton@dot.ca.gov

Public Information Office

District 10 logo

Phone: (209) 948-7977
Email: District10PublicAffairs@dot.ca.gov
Address: P.O. Box 2048, Stockton, CA 95201-2048