Interstate 5 Sperry Road Interchange
Project Description
The California Department of Transportation, in conjunction with Stanislaus County and the City of Patterson, proposes to construct improvements to the Interstate 5(I-5)/Sperry Road interchange, in Stanislaus County approximately 2.5 miles west of the City of Patterson. The City of Patterson is sponsoring the project and will be the lead for the design phase. The project would improve operations, enhance safety and increase the capacity of the interchange to accommodate the anticipated demand associated with recent and planned development adjacent to the interchange and in the City of Patterson.
The project proposes to upgrade the I-5/Sperry Road interchange. Improvements would include widening Sperry Road from 2-lane to 4-lane and widening or reconstructing the on- and off-ramps. Sperry Road will be widened in each direction between Del Puerto Canyon Road and 150 ft east of the California Aqueduct. Typically, the widening along Sperry Road is approximately 18 feet. However, additional widening is necessary at the approaches to the ramp intersections as well as the Rogers Road intersection to provide the required turn pockets.
Retaining walls will be constructed along both sides of Sperry Road under I-5, and the Sperry Road Bridge at the California Aqueduct will be widened to accommodate the wider roadway. Excavation will be required to construct the pavement structural sections and retaining walls needed to facilitate the roadway widening under the freeway. Existing tall embankment slopes will need to be widened along Sperry Road, east of the interchange.
Project Benefits
Purpose
- Increase the capacity of the interchange to accommodate existing and future traffic demands
- Improve operations and the movement of goods
- Enhance safety
Need
Improvements to the interchange are necessary to meet the increasing traffic demand associated with continued and planned commercial and industrial growth in the City of Patterson. Currently, the southbound off-ramp intersection operates at level of service (LOS) F in the PM peak period. By 2040, both ramp intersections are predicted to operate at LOS F during both the morning and afternoon peak traffic. Additionally, the project is anticipated to enhance the safety of motorists using this interchange, particularly the southbound off-ramp, which has an elevated incidence of vehicle accidents, as indicated in Section 4C Collision Analysis of this report.
Current Schedule
Project Approval & Environmental Document (M200)
9/22/20 (A)
Right of Way Certification (M410)
Fall 2024
Ready to List (M460)
Fall 2024
Approved Construction Contract (M500)
Spring 2024
Project Completion (M600)
Spring 2025
Funding Source
🌞
Project Status
Project is currently in Plans, Estimates, and Specifications (PS&E) phase.
Project Cost/Programmed (x$1,000):
Programed Project Cost | Capital $ | Support $ |
---|---|---|
Project Approval & Environmental Document | $737 | |
Plans, Specifications, & Estimates | $468 | |
Right of Way | $0 | $0 |
Construction | $17,102 | $216 |
Projected Cost as of June 26, 2023: | Planned $ | Expended $ |
---|---|---|
Project Approval & Environmental Document | $737 | $737 |
Plans, Specifications, & Estimates | $468 | $176 |
Right of Way | $0 | $ |
Construction | $216 | $ |
Project Manager
Sridhar Kidambi
Office Cell: (209) 986-1223
Email: Sridhar.Kidambi@dot.ca.gov
Public Information Office
Phone: (209) 948-7977
Email: District10PublicAffairs@dot.ca.gov
Address: P.O. Box 2048, Stockton, CA 95201-2048