Fish Springs Pavement

Project Information

The project will repave nearly 9 miles of pavement on U.S. 395 from 0.2 miles north of Elna Road, through the town of Big Pine, to the junction of State Route 168 E. Not only will repaving the road create a better driving experience for motorists and cyclists, but it will also defer the need for major and intrusive maintenance projects. Along with paving and asphalt work, major features of this project include Complete Streets improvements, ADA compliant sidewalk and curb ramps, striping, regulatory and warning signage, and a traffic census.

Project Map

Map detailing the project area for the Fish Springs Pavement Project

Project Cost

The estimated cost of this project is $40.8 million.

Project Timeline

Project Schedule (Subject to Change):

  • June 2022 - PA&ED
  • May 2024 - Right of Way Certification
  • June 21, 2024 - Ready to List
  • September 2024 - Advertise
  • January 2025 - Contract Approval
  • February 2025 - Beginning of Construction 

The Rebuilding CA Logo

 

U.S Highway 395 looking towards Bishop

Construction PIO Contact

Michael Lingberg

Public Information Officer
Construction
Caltrans District 9
(760) 920-0280

michael.lingberg@dot.ca.gov

Title VI Information

The California Department of Transportation (Caltrans) assures that no person shall, on the basis of race, color, or national origin, be excluded from participation in, be denied the benefits of, or be otherwise subjected to discrimination under any program or activity receiving Federal financial assistance, as required by Title VI of the Civil Rights Act of 1964, as amended, the Civil Rights Restoration Act of 1987, and Federal Executive Order 12898 (Federal Actions to Address Environmental Justice in Minority Populations and Low-Income Populations).

Caltrans will make every effort to ensure nondiscrimination in all of its programs and activities, whether they are federally funded or not, and that services and benefits are fairly distributed to all people, regardless of race, color, or national origin. In addition, Caltrans will facilitate meaningful participation in the transportation planning process in a nondiscriminatory manner.

Caltrans and You Title VI Brochure in various languages

An earthmover working on a Caltrans project. A project monitor stands in the foreground on the right.

Interested in bidding on this project?

Click the following link to view the 24-Month Advertise Look Ahead, which provides a two-year look ahead for capital construction projects based on their advertise month.

Information on upcoming projects can also be found at Contractor's Corner.