Contract 06-1C003(06A2799)

The responses to bidder's inquiries, unless incorporated into a formal addendum to the contract, are not a part of the contract and are provided for the bidder's convenience only. In some instances, the question and answer may represent a summary of the matters discussed rather than a word-for-word recitation. The availability or use of information provided in the responses to to bidder's inquiries is not to be construed in any way as a waiver of the provisions of Section 2-1.03 of the Standard Specifications or any other provision of the contract, the plans, Standard Specifications or Special Provisions, nor to excuse the contractor from full compliance with those contract requirements. Bidders are cautioned that subsequent responses or contract addenda may affect or vary a response previously given.

Q1) What is the minimum prime participation percentage?

A1) Attention is directed to section 5-1.13, “Subcontracting” of the Standard Specifications

Q2) Can the prime meet the minimum prime participation with material purchase?

A2) Attention is directed to section 5-1.13, “Subcontracting” of the Standard Specifications

Q3) Plan Sheet E-1 page 8 of 39– RC noted after the existing conduit at three points. Is the RC for the removal of cable /wire only or including something else such as abandoning conduit?

A3) The RC symbols on plan sheet E-1 shown below/after the listed Existing conduits and cables/wires is for the removal of the Existing conduits and cables/wires listed after the symbols. Refer to ANNOTATION on sheet Revised Standard Plan RSP ES-1A for the description for SYMBOL RC.

Q4) Please identify construction note 3 on legend for plan sheet E-8 page 15 of 39.

A4) Attention is directed to Addendum 1