Contract 05A2701 (05-1Q5604)

Responses to bidder inquiries, unless incorporated into formal addenda to the contract, are not a part of the contract, and are provided for the bidder’s convenience only. In some instances, the question and answer may represent a summary of the matters discussed rather than a word-for-word recitation. The availability or use of information provided in the responses to bidder inquiries is not to be construed in any way as a waiver of the provisions of 2-1.07, “Job Site and Document Examination,” of the Standard Specifications or any other provision of the contract, the plans, Standard Specifications, or special provisions nor to excuse the contractor from full compliance with those contract requirements. Bidders are cautioned that subsequent responses or contract addenda may affect or vary a response given previously.

Q1)  Can you please provide a response for the following questions related to the subject Caltrans contract.

  1. Will Caltrans require the temporary steel plates that cover the trench line to be recessed? If so, can a detail be provided.

A1)  Please refer to Standard Specifications Section 5-1.01 “ Control of Work”, “Where the means and methods to complete the work are not described in the Contract, choose the means and methods to complete the work”, and Section 7-1.04 “Public Safety” on temporary facilities requirements. If temporary steel plates are used, they are required to be recessed.