Contract 05-1K960(05A2236)

The responses to bidder's inquiries, unless incorporated into a formal addendum to the contract, are not a part of the contract and are provided for the bidder's convenience only. In some instances, the question and answer may represent a summary of the matters discussed rather than a word-for-word recitation. The availability or use of information provided in the responses to bidder's inquiries is not to be construed in any way as a waiver of the provisions of Section 2-1.03 of the Standard Specifications or any other provision of the contract, the plans, Standard Specifications or Special Provisions, nor to excuse the contractor from full compliance with those contract requirements. Bidders are cautioned that subsequent responses or contract addenda may affect or vary a response previously given.

Q1) Bid Item sheet has no quantities.

A1) Addendum 1 dated and posted today, 04-28-2020, includes the quantities.

Q2) for items 6, 7, and 8 you've added LF to the Bid sheet without specifying where this lineal foot is on the plans. Can you please specify where the extra lineal footage from the bid sheet is referenced to in the plans?

A2) Refer to Addendum No. 2, dated May 4, 2020.

Q3) Addenda 1 changed the bid date to May6. Addenda 2 states “the bid date remains the same May, 8”). Has the bid date changed to 5/8 or is it still 5/6?

A3) Refer to Addendum No 3, Dated May 5, 2020.