Contract 05-1F6405(05A2226)

The responses to bidder's inquiries, unless incorporated into a formal addendum to the contract, are not a part of the contract and are provided for the bidder's convenience only. In some instances, the question and answer may represent a summary of the matters discussed rather than a word-for-word recitation. The availability or use of information provided in the responses to bidder's inquiries is not to be construed in any way as a waiver of the provisions of Section 2-1.03 of the Standard Specifications or any other provision of the contract, the plans, Standard Specifications or Special Provisions, nor to excuse the contractor from full compliance with those contract requirements. Bidders are cautioned that subsequent responses or contract addenda may affect or vary a response previously given.

Q1) Plan Sheet L-3 & L-4 show a 2" conduit that crosses hwy 166 is this conduit already in place?

A1) The Contractor is to install the 2" conduit along with a pull tape.

Q2) The special provisions section 6 states that the contractor is to pickup the controller cabinets located at the Cambria Maintenance Station ,Will the contractor be required to have a forklift onsite or will the state load these onto the contractors trailer?

A2) State personnel or equipment will not be available to load the cabinets.

Q3) Can the cabinets be painted at the maintenance yard?

A3) Space will not be available in the maintenance yard to paint the cabinets.