Six Bridges Project - Georgia and Tennessee Streets to Re-Open

Published:

I-80 Six Bridges Project

Georgia St. Overcrossing To Reopen By May 6

Tennessee St. Overcrossing To Reopen on May 13

 

Solano County – Today, Caltrans announced that the Georgia St. overcrossing and the Tennessee St. overcrossing will reopen ahead of schedule. Both overcrossings are part of the I-80 Six Bridges Project, an SB1 project.

The Georgia St. overcrossing will reopen no later than May 6 while the Tennessee St. overcrossing will reopen on May 13. Both were scheduled to reopen later in May but due to favorable working conditions, the projects were completed ahead of schedule.

Completing the projects sooner than expected will allow Caltrans to accelerate the project timetable for the Redwood St. overcrossing, the last part of the I-80 Six Bridges Project.

Improvements on the Tennessee St. and Georgia St. overcrossings include:

  • Higher vertical clearance so modern trucks can pass underneath.
  • Improved pedestrian walkways making them safer to cross.

Learn more about I-80 Six Bridges project on our Caltrans Bay Area webpage.

Project Webpage: i80sixbridgesvallejo.com