I-80 Overnight Paving Operations – between Buchanan Street in Albany to Cutting Boulevard in Richmond

Published:

Schedule: Monday, May 12th through Monday, June 2nd, 8 p.m. to 5 a.m. each night

Contra Costa County – Caltrans District 4 will begin overnight paving operations on Interstate 80 (I-80) between Buchanan Street in Albany and Cutting Boulevard in Richmond. Work will take place in both directions on a scheduled basis over multiple weeks. Work includes Full paving of all lanes, including shoulders. The highway will remain open during operations with lane closures only during overnight hours.

Schedule and Details:

  • Working Days: Monday through Friday
  • Working Hours: 8:00 PM to 5:00 AM (nightly)

Eastbound I-80 Lane closures:

  • Dates: Monday, May 12 through Wednesday, May 21, 2025
  • Location: Buchanan Street to Cutting Boulevard

Westbound I-80 Lane closures:

  • Dates: Thursday, May 22 through Monday, June 2, 2025
  • Location: Cutting Boulevard to Buchanan Street

All work is weather dependent and subject to change.

Changeable Message Signs (CMS) will provide advance notice for motorists traveling in the area. Drivers may experience minor delays and are advised to plan ahead and allow extra time. Be work zone alert, drive with caution through the work zone. For 24/7 traffic updates, follow 511.org on Twitter. For real-time traffic, visit Caltrans QuickMap.