Redwood St. Overcrossing at Interstate 80 in Vallejo anticipated to re-open on Thurs., Sept. 1, ahead of construction schedule

Published:

(Caltrans completes sixth and final bridge as part of the I-80 Six Bridge Project)

Image showing improvements made to the Redwood Street overcrossing at Interstate 80 in Vallejo.SOLANO COUNTY – Caltrans is anticipating on reopening Redwood St. overcrossing at Interstate 80 (I-80) in Vallejo on Thursday, Sept. 1, 2022, to the traveling public.

Crews were able to increase the vertical clearance to 16 feet, 6 inches to meet the federal standards. 

Caltrans completed the I-80 Six Bridges Project ahead of schedule by three months, reducing the traffics impact to the residents of Vallejo and surrounding cities. 

Some construction work remains to be done, such as landscaping, barrier rail work and lane striping.

Improvements on all six overcrossings include:

  • Higher vertical clearance so modern trucks can pass underneath.
  • Improved pedestrian walkways making them safer to cross.

Learn more about I-80 Six Bridges project on our Caltrans Bay Area webpage.

Project Webpage: i80sixbridgesvallejo.com

For 24/7 traffic updates, please visit 511.org: https://twitter.com/511SFBay
For real-time information, please visit Caltrans QuickMap: http://quickmap.dot.ca.gov
Or follow Caltrans on Twitter at: https://twitter.com/CaltransD4

#BeWorkZoneAlert

###