Caltrans to Pave Highway 116 (Stage Gulch Road) East of Petaluma
From Lakeville Highway to Old Adobe Road
Full roadway closures scheduled for expedited project beginning April 19
SONOMA COUNTY - Caltrans will pave State Route 116 between Lakeville Highway and Old Adobe Road just east of Petaluma, a two-and-a-half-mile stretch of rural highway also known as Stage Gulch Road.
Ghilotti Brothers of San Rafael is the contractor for the $1million project to pave the two-lane highway. Caltrans will work an expedited schedule, starting Monday, April 19, 2021 and completing work in early May.
Caltrans will fully close the road on Monday and Tuesday during the project’s first week and Monday – Friday during the second week. (See schedule below.)
Residents and delivery vehicles destined to locations within the paving limits will be flagged through the closure points. Other traffic will be directed to a clearly signed detour around the project limits.
Detours: Westbound Traffic - Lakeville Highway to Frates Road to Adobe Road Eastbound Traffic - Adobe Road to Frates Road to Lakeville Highway
During the third week of the project, Caltrans will implement one-way traffic control. Motorists should expect delays or take the detour route to save time.
As part of the roadway rehabilitation, Caltrans will grind off the old pavement and replace it with a fresh layer of asphalt.
Closure Schedule
Week #1
Monday, April 19 - FULL CLOSURE - 7:00 PM-5:00 AM
Tuesday, April 20 - FULL CLOSURE 7:00 PM-5:00 AM
Wednesday, April 21 - One-Way Traffic Control 5:00 AM-2:00 PM
Thursday, April 22 - One-Way Traffic Control 5:00 AM-2:00 PM
Friday, April 23 - One-Way Traffic Control 5:00 AM-2:00 PM
Week #2
Monday – Friday, April 26 –30: FULL CLOSURE 7:00 PM– 2:00 PM,
Exception being that westbound Stage Gulch Road will open between 5:00 AM – 8:00 AM for the morning commute.
Week #3
Monday, May 3 – Friday, May 7 - One-way traffic control
No closures are scheduled for weekends. Closures may be subject to change. Caltrans expects completion of the project by the end of the third week. Some minor work may remain, but road closures are not expected.
For more information or to receive the latest updates on closures and construction progress: http://bit.ly/StageGulchRoad
For 24/7 traffic updates, go to 511.org: https://twitter.com/511SFBay You can also get real-time information on all State Highways in California on our Caltrans Quick Map: http://quickmap.dot.ca.gov/ Please be #WorkZoneAlert
Or follow Caltrans on Twitter at https://twitter.com/CaltransD4