Construction Forecast: December 30 - January 10, 2019

Tentative schedule:

In the next two weeks crews are scheduled to work on sewer and water main installation, installing a joint-utility trench, sidewalk and roadway replacement, light pole installation and permitted tree removal.

The work listed below is scheduled for daytimes, 7:00 a.m. to 8:00 p.m. Planned night work is italicized. The night shift for construction is 8:00 p.m. to 7:00 a.m. During this time, neighbors are advised to anticipate construction-related noise and vibrations as crews work diligently to complete necessary night work.

The following Van Ness Improvement Project construction forecast is subject to change. For more project details, please visit SFMTA.com/VanNess.

*No work is scheduled on the night of New Year’s Eve, Tuesday, December 31, or on New Year’s Day, Wednesday, January