U.S. Highway 50 South Lake Tahoe Safety Project

Project ID EA District County Route Funding Program
0319000072
 03-4H890 03 ED 050 SHOPP

Project Description

In South Lake Tahoe along U.S. Highway 50 (US 50), from State Route 89 (the “Y”) to Pioneer Trail. Install lighting on both sides of US 50, 4 pedestrian flashing signals at mid-block crosswalks, new signs, and green bike lane treatment to improve safety for pedestrians and bicyclists. The intersection of Johnson Boulevard and US 50 will be signalized and the roadway will be restriped.

Purpose and Need

The purpose of the proposed project is to improve pedestrian and bicyclist safety between the US 50/State Route 89 “Y” intersection and Pioneer Trail in South Lake Tahoe.

There is a need to reduce the number of fatalities and severe injuries from bicycle collisions along this stretch of the US 50 corridor. Most of the bicycle collisions occurred at night, and the project provides corrective action to address bicyclist-involved collisions.

Funding

This project was programmed in the 2018 State Highway Operation and Protection Program (SHOPP) and funded through the 20.XX.201.010 - Safety Improvement Program.


Cost Estimate

Total Project Cost $ 35,938,000

Schedule

Project Approval & Environmental Document 05/07/2021
Design Completed 10/12/2023
Advertise Project 12/11/2023
Begin Construction 04/17/2024
Completed Construction December 2025


Project News

Caltrans Seeks Feedback on Proposed U.S. Highway 50 Safety Project (03/05/2021)

Partnership

City of South Lake Tahoe

Project Contacts:

Berhane Tesfagabr, Project Manager, (916) 869-7335; berhane.tesfagabr@dot.ca.gov 
John O’Connell, Public Information Officer, (916) 701-9459; john.o'connell@dot.ca.gov

Map of Lake Tahoe project area