U.S. Highway 50 Multimodal Corridor Enhancement and Rehabilitation Project
Project Facts
Description
This comprehensive corridor project will construct High Occupancy Vehicle (HOV) lanes and rehabilitate pavement on US 50 from the US 50/I-5 Interchange (PM L0.2) to the US 50/Watt Avenue Interchange (PM R6.1) for a total of 14 lane miles.Project Benefits
- Provide an option for reliable peak period travel time.
- Use the highway facilities as efficiently as possible.
- Improve general traffic operations by reducing congestion and travel time.
- Improve bicycle and pedestrian access.
Closures
As of September 29, 2025 Construction is scheduled to continue along US-50 in Sacramento. The following lanes and ramps are scheduled to be CLOSED at nighttime:Overnight Work (9 p.m. to 5 a.m.)
Monday, September 29
• Eastbound 15th Street off-ramp and lane #3
• Eastbound X Street off-ramp lane #1
• Eastbound US 50 to northbound SR-51/Business 80/Capital City Freeway connector (2 hours nighttime closure)
• Eastbound US 50 to southbound SR-99 connector (2 hours nighttime closure)
• Westbound 16th Street off-ramp
Monday, September 29 to Wednesday, October 1, 2025
• One lane of northbound SR 99 to eastbound US 50 connector (11 p.m. to 5 a.m.)
Monday, September 29 to Friday, October 3, 2025
• Eastbound #3 and #4 lanes from 24th Street to 39th Street
• Westbound #3 and #4 lanes from Watt Avenue to Howe Avenue
• Eastbound 16th Street on-ramp
Monday, September 29 to Saturday, October 4, 2025
• Eastbound #3 and #4 lanes from Watt Avenue to Hornet Drive
• Eastbound 34th Street off-ramp
• Eastbound #3 and #4 lanes from 51st Street to Howe Avenue
• Eastbound 65th Street on-ramp
• Eastbound Howe Avenue off-ramp.
Monday, September 29 to Friday, October 10, 2025
• One lane of southbound SR 51/Business 80/Capital City Freeway to eastbound US 50 connector (11 p.m. to 5 a.m.)
Monday, September 29 to Monday, October 13, 2025
• Eastbound X Street on-ramp with auxiliary lane
Thursday, October 2 to Friday, October 10, 2025
• Eastbound #3 and #4 lanes from Howe Avenue to Mayhew Road
*All work is scheduled to begin as listed but is subject to change due to traffic incidents, weather, availability of equipment and/or materials, and other construction related issues.
- SHOPP Roadway Rehabilitation program. The total project cost for the long life pavement replacement, other highway asset upgrades and improving the vertical clearance at seven overcrossings is estimated at $368.9 million.
- Sacramento Measure A Transportation Sales Tax Program managed by Sacramento Transportation Authority (STA) for $52.2 million for the preliminary engineering, environmental studies (PA&ED), design, right-of-way work and construction.
- Solutions for Congested Corridors Program (SCCP) by State of California’s Senate Bill(SB) 1 - Road Repair and Accountability Act of 2017 for $90 million for construction.
- Total project cost: $511.1 million
Project Schedule
Circulate Draft Environmental Document -- September 2016 (completed)
Project Approval & Environmental Document – May 2017 (completed)
Request for Qualification for Design-Build Contract – February 2019 (completed)
Request for Proposal for Design-Build Contract – September 2019 (completed)
Award Design-Build Contract – April 2020
Complete Construction – July 2026
Partnership
Sacramento Transportation Authority (STA)
Sacramento Area Council of Governments (SACOG)
Sacramento Regional Transit (SacRT)
Project Contact
Daniel Kwong, P.E
Cell: (530) 713-3023
Email: Daniel.Kwong@dot.ca.gov
Sergio Ochoa Sanchez, Public Information Officer
Phone: (916) 826-3093
Email: Sergio.Ochoa.Sanchez@dot.ca.gov