PULGA 70 PROFILE CHANGE PROJECT

 Project ID

EA

District

County

Route

Funding Program

 0318000012  03-3H540  03 Butte  70  SHOPP

 

Project Description: 
Near Pulga on SR 70, from 0.8 mile west to 0.2 mile east of Shady Rest Area. Restore and repair damaged roadway by raising the existing vertical alignment by approximately five feet and protecting the embankment against future flooding with Rock Slope Protection (RSP) and a retaining structure.

Project Location Map:
map of sr70 pulga roadway

Purpose:

Restore and improve resiliency of the roadway by reducing the occurrence of flooding to protect the roadway against future flood damage and increase safety for the traveling public during adverse conditions.

Need:
This existing highway floods during high river flows causing erosion to the
embankment and undercutting of the roadway. Additionally, flooding in this section
leads to long term closures of the road resulting in long traffic delays and detours.

Funding:
The project is programmed in the State Highway Operation and Protection Program (SHOPP) under the funding from 20.XX.201.131, Major Damage program.

Total Project Cost:
Support Cost $11,300,000
Capital Cost $32,240,000
Total Project Cost $43,540,000

Schedule:

Project Approval & Environmental Document

December 7, 2020

Design Completed

July 25, 2022

Advertise Project

October 10, 2022

Begin Construction

 April 4, 2023

Complete Construction

December 2025

PROJECT CONTACTS:
Cameron Knudson, Project Manager, (530)218-1820
Megan Reese, Public Information Officer
(530) 682-6145