State Route 20 Stafford Way Intersection Safety Improvement
PROJECT DESCRIPTION:
In Yuba City, at the intersection of State Route 20 and Stafford Way, this project will install a new traffic signal, new intersection lighting, curb ramps, and pavement markings and delineation. The project will improve safety and reduce the number and severity of collisions at the intersection.
PROJECT LOCATION MAP:

PURPOSE:
The purpose of this project is to improve safety for motorists, bicyclists, and pedestrians at the intersection and reduce the number of serious injury collisions occurring at this location.
NEED:
The intersection experienced 33 collisions over a three-year period (July 1, 2017, to June 30, 2020), resulting in 28 injuries. The collision rate at this intersection is higher than the statewide average for similar facilities.
FUNDING:
This project is programmed in the 2024 State Highway Operation and Protection Program (SHOPP) and is funded in the 20.XX.201.010 Safety Improvements Program.
COST ESTIMATE:
Support Cost: $2,040,000
Capital Cost: $2,870,000
Total Project Cost: $4,910,000
SCHEDULE:
| Project Approval & Environmental Document | October 23, 2024 |
| Design Completed | June 25, 2025 |
| Advertise Project | August 11, 2025 |
| Begin Construction | November 3, 2026 |
| Complete Construction | October 2027 |
Press Release and Traffic Alerts
Traffic Alert: State Route 20 and Stafford Way Safety Improvement Project - Published March 30, 2026
Don't miss an update! Get the latest on this project straight to your inbox — Click here to join or email Megan Reese to get your email added.
Traffic Alert: State Route 20 and Stafford Way Safety Improvement Project - Published March 30, 2026
Don't miss an update! Get the latest on this project straight to your inbox — Click here to join or email Megan Reese to get your email added.
PROJECT CONTACTS:
Bikramjit Kahlon, Project Manager; 530-812-5049;
bikramjit.kahlon@dot.ca.gov
Megan Reese, Public Information Officer; 530-682-6145;
megan.reese@dot.ca.gov