Sacramento I-80 Ramp Rehabilitation
Project Facts
Description
Rehabilitate pavement at various connectors and ramps in Sacramento County, on I-80, from 0.2 miles west of W. El Camino O.C. to 0.2 miles east of 80/244 Separation. The project also proposes to upgrade curb ramps at work locations to meet the American with Disabilities Act (ADA) requirements.
Project Benefits
The purpose of this project is to preserve and extend the life of existing pavement and improve ride quality. The pavement condition of the included ramps and connectors varies, but each shows signs of major distress, and most if not all of them can be expected to develop unacceptable ride quality by the construction year.
Funding Breakdown
FUNDING/ESTIMATE (X1000):
Component PROGRAMMED
PA&ED $1,190
PS&E $1,220
RW Support $105
Construction Support $2,000
Right of Way Capital $25
Construction Capital $12,5111
Total $17,051
Project Schedule
Component Current
PA&ED 3/30/18
P&E 9/13/18
R/W CERT 9/6/18
RTL 9/28/18
APPROVE CONTRACT 3/4/19
BEGIN Construction 6/24/19
CONTRACT ACCEPT 3/23/20
Partnership
none
Project Contacts
Benjamin Hargrove
Project Manager
(530) 682-3679
Benjamin.Hargrove@dot.ca.gov
Dennis Keaton
Public Information Officer
(916) 825-5252
Dennis.Keaton@dot.ca.gov