Rio Vista Bridge Preservation Project
Project Facts
Project ID | EA | District | County | Route | Funding Program |
---|---|---|---|---|---|
0319000026 | 4H690 | 03 | SAC | 012 | Major Damage Restoration |
Description
This project is located in and near Rio Vista, at the Sacramento River Bridge No. 23-0024; also, in Solano County from PM 26.3 to PM 26.4.
The Rio Vista Bridge (Bridge No. 23 0024) is a two-lane vertical-lift bridge with a lift span of approximately 270 feet and a structure length of 2890 feet. The bridge has recently experienced electrical and mechanical failures resulting in multiple bridge closures affecting roadway and marine traffic. This project provides emergency repairs and improve reliability of the bridge electrical and mechanical operational systems. The Director’s Order was approved August 20, 2018.
Need
The Rio Vista Bridge became inoperable on August 9, 2018 when the bridge lift span gear assemblies were damaged. Initially the bridge was stuck in the up position impacting vehicular traffic until it was lowered after several days, which in-turn impacted the maritime traffic. The bridge is a regionally significant commerce passageway, as it represents the only way for cargo ships to get in and out of the Ports of West Sacramento and Stockton.
Purpose
The purpose is to provide for immediate/emergency repairs and improve reliability of the bridge electrical and mechanical operational systems. It also includes assessing and repairing and/or upgrading mechanical and electrical components (motors, gears, powered backup systems, lift cables, ropes, power and communication lines, modern control systems, etc.); Expert and peer review to advise designers and contractors on systems and repair methods; Upgrading signage and lighting; and placing a new lightweight bridge deck on the lift span.
Funding
Project funded from State Highway Account (SHA) under 20.XX.201.130 Major Damage Restoration.
Cost Estimate
Component | Support | Capital |
---|---|---|
PA&ED | n/a | n/a |
PS&E | n/a | n/a |
Right of Way | n/a | $100,000 |
Construction | $7,900,000 | $24,250,000 |
Total | $7,900,000 | $24,350,000 |
Schedule
Begin Construction: 08/13/18
Complete Construction: 1/12/22
End Construction: 3/15/2024
Project Contacts
Dennis Keaton, PIO, (916) 825-5252
Soka Soka, Project Manager, (530) 741-5300