Glenn Highway 162 Butte City Bridge Replacement

Project Facts

Description

  • Replace the existing steel bridge built in 1948 with a new bridge with standard 12-foot traffic lanes and 8-foot shoulders.
  • Replace the existing viaduct with a new facility featuring standard 12-foot traffic lanes and 8-foot shoulders.
  • Construct 8- to 14-foot shoulders on State Route 162 through Butte City in Glenn County.

Project Benefits

This project will preserve and extend the useful life of the existing roadway throughout the project limits and to replace the existing Sacramento River Bridge and viaduct to meet current design standards.

Funding

Estimated Total Project Cost - $114 million

Project Schedule

Environmental Clearance: June 2019
Design Completion: January 2021
Begin Construction: February 2022
Finish Construction: December 2026  

Project Contacts

Julio Torreiro-Casal, Project Manager 
Phone: (530) 812-4818 
Email: julio.torreiro-casal@dot.ca.gov 

Megan Reese, Public Information Officer 
Phone: 530-682-6145
Email: Megan.Reese@dot.ca.gov