Echo Summit Sidehill Viaduct
Project Facts
Description
This $14.1 million project will replace the Echo Summit Bridge (Br#25-0044), which is located in El Dorado County 7 miles west of the city of South Lake Tahoe along U.S. Highway 50 near Echo Summit. At the project location, the road width is very narrow and confined by a vertical rock cut slope on the mountain side and a nearly vertical downward slope on the Basin side.
Project Benefits
This project will address deficient structural components in a bridge that is in poor condition.
Project Schedule
Environmental Document Completed -- December 2016
Right of Way Acquisition Completed -- Spring 2018
Design Completed -- Spring 2018
Advertise -- Summer 2018
Begin Construction -- Spring 2019
Expected Completion – December 2020
Partnership
Tahoe Regional Planning Agency (TRPA)
Project Contact
Clark Peri, Project Manager
Phone: (916) 825-8168
Email: clark.peri@dot.ca.gov
Steve Nelson, Tahoe Basin Outreach Coordinator
Phone: (530) 701-9459
Email: steve.nelson@dot.ca.gov
Map
Project Documents
- Pre-Bid Meeting Roster (PDF)
- Echo Summit Sidehill Viaduct Replacement Project Presentation 10-26-16 (PDF)
- Notice of Preparation of a Draft Environmental Impact Report (PDF)
- Notice of Intent to Adopt a Mitigated Negative Declaration (PDF)
- Public Meeting For Echo Summit (PDF)
- Initial Study with Proposed Mitigated Negative Declaration (PDF)
- Draft Project Report Bridge Replacement (PDF)
- Final Project Report (PDF)
Press Releases
- Highway 50 at Echo Summit Reopened Under One-Way Traffic Control
- Public Meeting in Placerville for Echo Summit Bridge Project
- Public Meeting in Placerville for Echo Summit Bridge Project
- Public Meeting Set for Proposed Echo Summit Bridge Replacement Project